GCB-Final | 5/4/2015 | 5/5/2015 | 5/5/2015 | A | PASS |
Mike Jordan
|
|
|
Brandon ###-####. All issues resolved.
|
GCB-Final | 5/1/2015 | 5/4/2015 | 5/4/2015 | A | FAIL |
Mike Jordan
|
|
|
Brandon ###-####. Install the seals on the doors in the fire barrier wall. Remove all dead bolts and key locking hardware. Provide code compliant handrails for stairs.
|
FIRE-Final Inspection | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
|
|
|
*Jim Poe with BFD performing GCB life safety inspection.
|
GCB-Fire Wall | 4/16/2015 | 4/16/2015 | 4/17/2015 | P | CANC |
Dave Hannah
|
|
|
Curt ###-####
|
GCB-Fire Wall | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | PASS |
Dave Hannah
|
|
|
Curt Barber ###-#### top of wall fixed removed insulation and replaced with rock wool
|
GCB-Fire Wall | 4/10/2015 | 4/13/2015 | 4/13/2015 | A | FAIL |
Dave Hannah
|
|
|
Curt ###-#### needs to run sheetrock to roof deck
|
GCB-Fndatn/slab ins/fld vent | 4/3/2015 | 4/6/2015 | 4/6/2015 | A | PASS |
Mike Jordan
|
|
|
Contractor ###-####. Footings for new pit walls ok.
|
GCB-Fndatn/slab ins/fld vent | 4/1/2015 | 4/2/2015 | 4/2/2015 | A | NR |
Jim Sly
|
|
|
Brandon ###-#### - rebar and contcrete insp. (inside buiding) Not completely done with rebar.
|
GCB-Fire Wall | 3/31/2015 | 4/2/2015 | 4/2/2015 | A | PART |
Jim Sly
|
|
|
Curt ###-#### 1st layer rated wall.....OK. Starting 2nd layer........Verified staggered joints.
|
GCB-Framing | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | PASS |
Phil Shearer
|
|
|
Curt ###-#### - requested call ahead and insp. after 1p.m.
|
GCB-Framing | 3/20/2015 | 3/23/2015 | 3/23/2015 | P | PART |
Dave Hannah
|
|
|
Curt ###-#### up stairs bathroom ok
|
Issue and Courier | | | 3/13/2015 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | | 1/12/2015 | 3/12/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/10/2015 | | 3/12/2015 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 3/6/2015 | | 3/10/2015 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 3/10/2015 | | DONE |
Candy A. Nichols
|
|
|
received the 3rd set of plans from GC. We already had the other 2 sets-took to Sam Z
|
Routing - PLAN CHECK | 3/6/2015 | | 3/6/2015 | | PEND |
Sam Zahorka
|
|
|
Pending Mechanical COMcheck and mechanical review to pass.
|
Telephone call | | | 3/6/2015 | | DONE |
Sam Zahorka
|
|
|
Called the architect and requested the COMcheck for mechancial. He said he would get it emailed to me.
|
Routing - PLAN CHECK | 2/25/2015 | | 3/6/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 3/5/2015 | | DONE |
Candy A. Nichols
|
|
|
resubmittal received letter from Broncoelite, calcs, vents and 2 each of sheet g1.0, a1-0, a2.0, a2.1, a4.0, & m-200-took to Sam Z
|
Routing - FIRE | 2/23/2015 | 2/23/2015 | 2/25/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Meeting | | | 2/25/2015 | | DONE |
Sam Zahorka
|
|
|
Met with the architect and the tenant to discuss plan review comments/corrections. THis meeting was outside the Garden City meeting agreement times. 1-hour was needed for this meeting.
|
Routing - PLAN CHECK | 2/19/2015 | | 2/23/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 2/23/2015 | | 2/23/2015 | | FAIL |
Troy James
|
|
|
|
Plan resubmittals received | | | 2/19/2015 | | DONE |
Candy A. Nichols
|
|
|
resubmittals received 3 each-G1.0, A0.00,A1.0, A2.0, A2.1,A3.0,A4.0, A4.1, M-100, M-200-RESPONSE LETTER-com check-took to Sam Z
|
Routing - FIRE | 1/27/2015 | | 1/28/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed architect plan review report. Attached report to case.
|
1st review completed | | | 1/28/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 1/14/2015 | | 1/27/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 1/13/2015 | | 1/14/2015 | | FAIL |
Troy James
|
|
|
emailed corrections to applicant and egineer
|
Routing - Public Works | 1/12/2015 | 1/12/2015 | 1/13/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | | 1/9/2015 | | DONE |
|
|
|
via Garden City Web Service
|