GCB-Final | 9/21/2015 | 9/24/2015 | 9/24/2015 | P | PASS |
Mike Jordan
|
|
|
Breanne ###-####
|
FIRE-Final Inspection | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Katie Marron
|
|
|
Verified previous items were corrected. Life safety pass.
|
FIRE-Final Inspection | 9/22/2015 | 9/23/2015 | 9/23/2015 | A | FAIL |
Katie Marron
|
|
|
Main door exit sign to be repaired. Hardware for cooler to be replaced with single action non grasping.
|
Plan assigned to (SRZ) | | 3/19/2015 | 5/1/2015 | | DONE |
Sam Zahorka
|
|
|
1st review completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2015 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 5/1/2015 | | DONE |
|
|
|
|
Routing - Plumbing Review | 4/27/2015 | | 4/30/2015 | | PASS |
Bill VanDegrift
|
|
|
May require additional backflow protection on water service.
|
Routing - PLAN CHECK | 4/6/2015 | | 4/27/2015 | | PASS |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 4/22/2015 | | DONE |
|
|
|
resubmittals received 3 sets of T1.1, A3.1, P0.0, P2.1 & P3.0-1 response letter-took to Sam Z
|
Routing - FIRE | 3/30/2015 | 3/30/2015 | 4/6/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
1st review completed | | | 3/27/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/23/2015 | | 3/27/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 3/19/2015 | | 3/23/2015 | | PASS |
Troy James
|
|
|
Brewing Kettle is electric. No gas fired equipment.
|
Routing - Plumbing Review | 3/23/2015 | | 3/23/2015 | | FAIL |
Bill VanDegrift
|
|
|
An engineered set of plumbing plans are required for review.
|
Routing - Public Works | 3/19/2015 | 3/19/2015 | 3/19/2015 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 3/18/2015 | | DONE |
|
|
|
via Garden City Web Service
|