GCB-Final | 6/29/2015 | 6/29/2015 | 6/29/2015 | P | PASS |
Jim Sly
|
|
|
Carolyn ###-#### MTI special inspection of bolting for racking approved......File # B15066C
|
GCB-Final | 6/23/2015 | 6/23/2015 | 6/23/2015 | P | NR |
Jim Sly
|
|
|
Caroline ###-#### - requested call ahead Not Ready.........Called Caroline and asked her if she had the paperwork on site from the Special inspection agency for bolting of rack system. She said no. Will call when paperwork, showing approval is on site.
|
GCB-Final | 6/18/2015 | 6/19/2015 | 6/19/2015 | A | PART |
Mike Jordan
|
|
|
Caroline ###-####. Needs special inspection on insatlled anchors. Everything else ok.
|
FIRE-Final Inspection | 6/17/2015 | 6/18/2015 | 6/18/2015 | P | PASS |
Katie Marron
|
|
|
Fire Life Safety pass.
|
GCB-Final | 6/16/2015 | 6/16/2015 | 6/17/2015 | P | NR |
Jim Sly
|
|
|
Caroline ###-#### - storage racks Not ready.....Need fire final approval.
|
Plan assigned to (SRZ) | | 3/30/2015 | 5/1/2015 | | DONE |
Sam Zahorka
|
|
|
1st IBC review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2015 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 5/1/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/10/2015 | | 4/20/2015 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 4/20/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - FIRE | 3/31/2015 | 3/30/2015 | 4/10/2015 | | PASS |
Scott Arellano
|
|
|
Approved with gneral storage conditions. Cumulative storage is less than 500 sq.ft; therefore the provisions of IFC chapter 32 are not applicable. The building plan or application does not indicate if this is a fire sprinklered building. Storage shall be maintained 2 feet or more below the ceiling in nonsprinklered areas of buildings or a minimum of 18 inches below sprinkler head deflectors in sprinklered areas of buildings, as applicable.
|
Routing - Public Works | 3/30/2015 | 3/30/2015 | 3/31/2015 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 3/27/2015 | | DONE |
|
|
|
via Garden City Web Service
|