Permit Information
Permit NumberGCB15-00046
StatusFinaled
Name Roth Homes
Site Address 10199 W CARLTON BAY
Project NameBLD2015-00046
Customer Number 
ePlanReviewNo
Description
Lot 14 Townhouse - To construct a new 2,421 square foot, Two story (967 square foot 1st story / 1,454 square foot 2nd story), Three bedroom, two and one half bathrooms, single family dwelling townhouse with an attached garage, a 33 square foot covered patio, and a 282 square foot courtyard. All work per the approved plans, attached plan review report, adopted codes, and all other reviewing agencies approvals. 1-hour fire-resistance construction is required on all projections closer than 3 feet to the property line. Distance to property line for fire rated construction is measured from the finished exterior of the exterior wall. Any walls less than 3' from the property line are required to have 1-hour fire-resistance construction. This structure is located in the floodplain. The elevation certificate is attached to the plans. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final12/22/201512/22/201512/22/2015PPASS
DetailsMike Jordan
Manny ###-####. Structural final ok.
Plan resubmittals received  10/21/2015 DONE
new manual j report
Routing - Mechanical Review10/21/2015 10/21/2015 PASS
DetailsTroy James
resubmitted manual j report
GCB-Framing10/2/201510/5/201510/5/2015ACANC
DetailsMike Jordan
Manny ###-####
GCB-Energy10/2/201510/5/201510/5/2015APASS
DetailsMike Jordan
Manny ###-####
GCB-Framing9/29/20159/30/20159/30/2015PPASS
DetailsJim Sly
Manny ###-####
GCB-Shearwall9/29/20159/30/20159/30/2015PPASS
DetailsJim Sly
Manny ###-####
Plan resubmittals received  9/23/2015 DONE
new manual j report
Routing - Mechanical Review9/23/2015 9/23/2015 PASS
DetailsTroy James
resubmitted manual j report
GCB-Courtesy9/16/20159/16/20159/16/2015PDONE
DetailsJim Sly
Manny ###-####
GCB-Fire Wall9/8/20159/8/20159/8/2015PFAIL
DetailsTony Young
Manny ###-####,, correction notice posted
GCB-Shearwall9/8/20159/8/20159/8/2015PFAIL
DetailsTony Young
Manny ###-####,, correction notice posted
GCB-Footing6/24/20156/24/20156/24/2015PPASS
DetailsDave Hannah
###-####
GCB-Fndatn/slab ins/fld vent6/23/20156/24/20156/24/2015APASS
DetailsDave Hannah
###-####
GCB-Footing6/19/20156/22/20156/22/2015PPART
DetailsTony Young
###-####,, work in progress,, need to be min 8" thick on main footings
GCB-Footing6/18/20156/19/20156/19/2015PNR
DetailsMike Jordan
###-####. No one on site, work not started.
Plan assigned to (SRZ) 4/17/20155/1/2015 DONE
DetailsSam Zahorka
Routing - PLAN CHECK4/22/2015 5/1/2015 PASS
DetailsSam Zahorka
1st review completed  5/1/2015 DONE
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  5/1/2015 DONE
DetailsSam Zahorka
Issue and Courier  5/1/2015 DONE
Routing - Mechanical Review4/17/2015 4/22/2015 PASS
DetailsTroy James
Application received  4/15/2015 DONE
via Garden City Web Service