GCB-Final | 2/16/2016 | 2/17/2016 | 2/17/2016 | A | PASS |
Dave Hannah
|
|
|
John ###-####
|
GCB-Final | 1/25/2016 | 1/27/2016 | 1/27/2016 | A | PART |
Dave Hannah
|
|
|
John ###-#### - final for C of O ok for temp occ
|
FIRE-Final Inspection | 1/25/2016 | 1/26/2016 | 1/26/2016 | P | PASS |
Katie Marron
|
|
|
Fire Life Safety Pass. Verified all exterior egress lighting, door hardware, and sprinkler escutcheons/ceiling tiles.
Extinguishers missing from mezzanines in production area. Contractor receiving two this afternoon. To be verified by Building Inspector.
Occupant Load signs present, not hung.
|
GCB-Courtesy | 1/20/2016 | 1/20/2016 | 1/20/2016 | P | PASS |
Dave Hannah
|
|
|
John ###-#### - requested Dave
|
FIRE-Final Inspection | 1/14/2016 | 1/15/2016 | 1/15/2016 | A | PART |
Katie Marron
|
|
|
Temporary Occupancy Ok for first floor business area. No general public allowed.
Verified exit hardware and fire extinguishers in this temporary occ. area. Verified exit signs, emergency lighting and ceiling tiles are in place throughout bldg.
At final will need to verify outside egress lighting, Occupant load sign, fire extinguishers in all other area, all remaining door hardware.
|
GCB-Final | 1/14/2016 | 1/14/2016 | 1/14/2016 | P | PART |
Dave Hannah
|
|
|
John ###-#### - Final for Temp C of O Only ok for temp occ but no general public owner and staff only
|
GCB-Ceiling Grid | 1/12/2016 | 1/12/2016 | 1/12/2016 | P | PASS |
Jim Sly
|
|
|
John ###-#### Grid OK.
|
GCB-Courtesy | 1/6/2016 | 1/6/2016 | 1/7/2016 | P | DONE |
Dave Hannah
|
|
|
John ###-#### - requested call ahead
|
FIRE-Conference | 1/6/2016 | 1/6/2016 | 1/6/2016 | P | DONE |
Troy Cobbley
|
|
|
John Chehey and I went over life safety requierments for a temporary occupancy for the "Tasting" area. I deferred him to Scott Arellano for the actual temporary request. I noted that the building address of 2900 chinden is incorrect on the computer as well.
|
FIRE-Sprinkler Rough-in | 12/31/2015 | 12/31/2015 | 12/31/2015 | A | PASS |
|
|
|
All hard lid area ok to cover EXCEPT West stairway.
|
GCB-Energy | 12/21/2015 | 12/21/2015 | 12/21/2015 | P | PASS |
Dave Hannah
|
|
|
John ###-####
|
GCB-Energy | 12/17/2015 | 12/18/2015 | 12/18/2015 | P | PART |
Dave Hannah
|
|
|
John ###-####second floor offices ok to cover
|
GCB-Energy | 11/30/2015 | 12/1/2015 | 12/2/2015 | P | PART |
Dave Hannah
|
|
|
John ###-#### ok to cover south area of bldg
|
GCB-Framing | 11/25/2015 | 11/30/2015 | 11/30/2015 | A | PASS |
Mike Jordan
|
|
|
John ###-####. interior and exterior shear walls, 1st floor ok, all holdowns installed. ok to insulate.
|
GCB-Shearwall | 11/17/2015 | 11/18/2015 | 11/18/2015 | A | PART |
Dave Hannah
|
|
|
John ###-#### ext sheeting and nailing ok butneeds to install holddowns
|
GCB-Framing | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | PART |
Mike Jordan
|
|
|
John ###-####. Work in progress on structural steel welding. Pending special inspection approval prior to cover.
|
GCB-Fndatn/slab ins/fld vent | 9/9/2015 | 9/11/2015 | 9/11/2015 | A | PASS |
Phil Shearer
|
|
|
John ###-####. Pending MTI inspection
|
GCB-Footing | 9/1/2015 | 9/2/2015 | 9/2/2015 | A | PART |
Phil Shearer
|
|
|
Line D footing stem wall line 1 Pending MTI inspection
|
GCB-Fndatn/slab ins/fld vent | 8/24/2015 | 8/25/2015 | 8/25/2015 | A | PART |
Jim Sly
|
|
|
John ###-#### All walls except .......S. wall ....E. end. Wall that parallels Green Belt. Center wall. OK pending M T I special inspections, tests and approvals.
|
GCB-Footing | 8/5/2015 | 8/5/2015 | 8/6/2015 | P | PART |
Jim Sly
|
|
|
Jordan ###-#### Perimeter and 2 column pads OK pending MTI special inspection, tests and approvals.
|
Issue and Courier | | | 7/13/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | | 5/14/2015 | 7/12/2015 | | DONE |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 6/26/2015 | | 7/12/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/6/2015 | | 7/8/2015 | | PASS |
Carl D Madsen
|
|
|
resubmittals dated 7/2/15
Received approval letter on 7/8/15
|
Plan resubmittals received | | | 7/2/2015 | | DONE |
|
|
|
resubmittals received 3 of each sheets S0.2, S2.0, S8.1, S9.1, S9.2, S9.3-engineering calcs & 1 response letter-took to Carl M
|
Plan resubmittals received | | | 6/30/2015 | | DONE |
|
|
|
resubmittals received 3 sets of sheet A2.1, A6.0, A9.0 and a response letter-took to carl M
|
Routing - FIRE | 6/25/2015 | 6/25/2015 | 6/26/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to plans
|
Plan resubmittals received | | | 6/26/2015 | | DONE |
|
|
|
resubmittals-received 3 sheets of F2.00 & 1 transmittal letter-took to Carl M
|
Routing - PLAN CHECK | 6/12/2015 | | 6/25/2015 | | FAIL |
Carl D Madsen
|
|
|
Accessible route is not adequately addressed.
|
Plan resubmittals received | | | 6/25/2015 | | DONE |
|
|
|
resubmittals recieved 3 sets of sheet A2.1 & F2.00-1 response letter - Took to Carl M
|
Routing Off Site - STRUCTURAL | 6/2/2015 | | 6/25/2015 | | FAIL |
Carl D Madsen
|
|
|
Forwarded comments to Larson Architects
|
Plan resubmittals received | | | 6/24/2015 | | DONE |
|
|
|
Resubmittals received 3 of each sheet A0.0, C1.20,A0.21, A2.1, A2.2, A2.3, A3.1, A6.0, A6.3, A6.5, A7.0, A9.0,A9.1, AS5.0, AS6.0, E0.1, E2.1L, E2.2L & 1 response packet-took to Carl M
|
Routing - FIRE | 6/10/2015 | 5/14/2015 | 6/12/2015 | | FAIL |
Katie Marron
|
|
|
Comments attached to plan and emailed to architect
|
1st review completed | | | 6/12/2015 | | FAIL |
|
|
|
Failed Fire and Plan Check
|
Routing - Plumbing Review | 6/8/2015 | | 6/10/2015 | | PASS |
Daryl Spivey
|
|
|
May require additional backflow protection on installed equipment.
|
Routing - PLAN CHECK | 5/21/2015 | | 6/8/2015 | | FAIL |
Carl D Madsen
|
|
|
E-Mailed Larson architects and Garden City. 6-8-2015
|
Plan resubmittals received | | | 6/2/2015 | | DONE |
|
|
|
received thge 3rd set of plans for outside engineering plus 3 struc cals, 2 geotech reports and a cover sheet-took to Carl M
|
Routing - Mechanical Review | 5/18/2015 | | 5/21/2015 | | PASS |
Troy James
|
|
|
|
Routing - Public Works | 5/14/2015 | 5/14/2015 | 5/18/2015 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 5/12/2015 | | DONE |
|
|
|
via Garden City Web Service
|