GCB-Final | 2/19/2016 | 2/22/2016 | 2/22/2016 | P | PASS |
Dave Hannah
|
|
|
Grey ###-#### - lockbox in back: 8223
|
GCB-Framing | 9/14/2015 | 9/15/2015 | 9/15/2015 | P | PASS |
Jim Sly
|
|
|
Grey ###-#### Frame and Energy......OK.
|
GCB-Framing | 9/10/2015 | 9/11/2015 | 9/11/2015 | A | PART |
Phil Shearer
|
|
|
Grey ###-####. Straps over ducked through top plate
|
Plan resubmittals received | | | 9/3/2015 | | DONE |
|
|
|
new manual j report
|
Routing - Mechanical Review | 9/3/2015 | | 9/3/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
GCB-Shearwall | 8/21/2015 | 8/24/2015 | 8/24/2015 | A | PASS |
Jim Sly
|
|
|
Grey ###-####
|
GCB-Energy | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PART |
Dave Hannah
|
|
|
Grey ###-#### foundation insulation ok
|
GCB-Fndatn/slab ins/fld vent | 8/6/2015 | 8/6/2015 | 8/6/2015 | P | PASS |
Dave Hannah
|
|
|
Heron ###-####
|
GCB-Footing | 8/5/2015 | 8/5/2015 | 8/5/2015 | P | PASS |
Jim Sly
|
|
|
Heron ###-####
|
Plan assigned to (CDM) | | 5/26/2015 | 8/3/2015 | | DONE |
Carl D Madsen
|
|
|
First review completed
|
Issue and Courier | | | 7/13/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/12/2015 | | 7/12/2015 | | PASS |
Carl D Madsen
|
|
|
Nonbuild agreement received fo projections over the property lines.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/26/2015 | | 5/30/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 5/30/2015 | | DONE |
|
|
|
|
Routing - Mechanical Review | 5/26/2015 | | 5/26/2015 | | PASS |
Troy James
|
|
|
|
Application received | | | 5/22/2015 | | DONE |
|
|
|
via Garden City Web Service
|