GCB-Final | 3/29/2016 | 3/30/2016 | 3/30/2016 | A | PASS |
Jim Sly
|
|
|
Mike ###-####
|
GCB-Shearwall | 10/28/2015 | 10/28/2015 | 10/28/2015 | P | PASS |
Mike Jordan
|
|
|
Mike ###-####. Interior wall bracing ok
|
GCB-Energy | 10/19/2015 | 10/21/2015 | 10/21/2015 | A | PASS |
Dave Hannah
|
|
|
Mike ###-####
|
GCB-Framing | 10/15/2015 | 10/16/2015 | 10/16/2015 | A | PASS |
Jim Sly
|
|
|
Mike ###-####
|
GCB-Shearwall | 9/9/2015 | 9/9/2015 | 9/9/2015 | P | PASS |
Dave Hannah
|
|
|
Mike ###-#### - exterior shear
|
GCB-Stem wall | 7/16/2015 | 7/16/2015 | 7/17/2015 | P | PASS |
Dave Hannah
|
|
|
Rob ###-####
|
GCB-Footing | 7/8/2015 | 7/9/2015 | 7/9/2015 | A | PASS |
Dave Hannah
|
|
|
Rob ###-####
|
Plan assigned to (CDM) | | 6/10/2015 | 6/19/2015 | | DONE |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 6/19/2015 | | 6/19/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 6/19/2015 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 6/11/2015 | | 6/16/2015 | | FAIL |
Carl D Madsen
|
|
|
Engineering required for lateral design.
|
1st review completed | | | 6/16/2015 | | FAIL |
|
|
|
|
Routing - Mechanical Review | 6/10/2015 | | 6/11/2015 | | PASS |
Troy James
|
|
|
|
Application received | | | 6/9/2015 | | DONE |
|
|
|
via Garden City Web Service
|