GCB-Final | 6/6/2016 | 6/7/2016 | 6/7/2016 | A | PASS |
Jim Sly
|
|
|
Doug ###-####
|
GCB-Energy | 12/15/2015 | 12/16/2015 | 12/16/2015 | A | PASS |
Dave Hannah
|
|
|
Doug ###-####
|
GCB-Framing | 12/10/2015 | 12/10/2015 | 12/11/2015 | P | PASS |
Dave Hannah
|
|
|
|
GCB-Framing | 12/10/2015 | 12/10/2015 | 12/10/2015 | A | CANC |
Dave Hannah
|
|
|
|
GCB-Framing | 12/9/2015 | 12/9/2015 | 12/10/2015 | A | CANC |
Dave Hannah
|
|
|
Doug ###-####
|
GCB-Framing | 12/9/2015 | 12/9/2015 | 12/9/2015 | A | PEND |
Dave Hannah
|
|
|
Doug ###-#### walked project with builder made list of items to correct.
|
Plan resubmittals received | | | 11/25/2015 | | DONE |
|
|
|
new manual j report
|
Routing - Mechanical Review | 11/25/2015 | | 11/25/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
CHANGE STATUS TO (ISS) | | | 11/25/2015 | | DONE |
|
|
|
|
GCB-Fndatn/slab ins/fld vent | 9/3/2015 | 9/3/2015 | 9/3/2015 | P | PASS |
Jim Sly
|
|
|
Dave ###-#### - insp. record card in box behind temp. power
|
GCB-Footing | 8/27/2015 | 8/27/2015 | 8/27/2015 | P | PASS |
Jim Sly
|
|
|
Greg ###-####
|
Plan assigned to (CDM) | 7/13/2015 | 7/13/2015 | 8/3/2015 | | DONE |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 7/27/2015 | | DONE |
|
|
|
Engineering calcs received
|
Routing - PLAN CHECK | 7/27/2015 | | 7/27/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/27/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 7/27/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/17/2015 | | 7/24/2015 | | FAIL |
Carl D Madsen
|
|
|
Failed pending structural calculations.
|
1st review completed | | | 7/24/2015 | | FAIL |
|
|
|
|
Routing - Mechanical Review | 7/13/2015 | | 7/17/2015 | | PASS |
Troy James
|
|
|
|
Application received | | | 6/24/2015 | | DONE |
|
|
|
via Garden City Web Service
|