Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberGCB15-00094
StatusFinaled
Name French Homes Inc.
Site Address 442 E 51ST
Project NameBLD2015-00095
Customer Number 
ePlanReviewNo
Description
(TOWNHOUSE) Permit for the construction of a new 1,613 sq. ft. 2 story (First story 598 sq. ft. second story 1,015 sq. ft.) with a 390 sq. ft. attached garage. This building consists of 3 bedrooms and 3 1/2 bathrooms. Structure to be constructed per the approved plans and the attached engineering. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final3/11/20163/11/20163/14/2016PPASS
DetailsDave Hannah
Dan ###-####
GCB-Energy12/18/201512/18/201512/18/2015PPASS
DetailsDave Hannah
Dan ###-####
GCB-Framing12/15/201512/16/201512/16/2015PPASS
DetailsDave Hannah
Dan ###-####
GCB-Shearwall11/19/201511/19/201511/19/2015PPASS
DetailsDave Hannah
Dan ###-####
GCB-Fire Wall11/13/201511/16/201511/16/2015APART
DetailsDave Hannah
Dan ###-#### first layer of sheetrock vert ok to cover.
GCB-Fndatn/slab ins/fld vent11/13/201511/16/201511/16/2015APASS
DetailsDave Hannah
Dan ###-#### pass received engineering on ftgs
GCB-Fndatn/slab ins/fld vent9/8/20159/8/20159/8/2015PFAIL
DetailsDave Hannah
James ###-#### foundation wall not on footing in several places.
GCB-Footing9/1/20159/2/20159/3/2015PPASS
DetailsDave Hannah
James ###-#### - requested 12p.m. insp.
GCB-Footing8/31/20159/1/20159/1/2015PNR
DetailsDave Hannah
James ###-#### - requested 2:30p.m. insp.
Plan assigned to (CDM)7/9/20157/9/20158/28/2015 DONE
DetailsCarl D Madsen
First review completed
Routing - PLAN CHECK8/21/2015 8/21/2015 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  8/21/2015 DONE
Issue and Courier  8/21/2015 DONE
Plan resubmittals received  8/18/2015 DONE
resubmittals received 3 sets of sheet-Ele plan/partition wall, ele plan/sectopm S5.0.10, fire rated soffits & eave detail, fnd plan/typical wall section, elevation, main level, fire/soffit/eave/roof framing, elevation, upper level & 3 sets of struc calcs & 1 cover sheet-took to Carl M
1st review completed  7/31/2015 FAIL
Routing - Mechanical Review7/9/2015 7/13/2015 PASS
DetailsTroy James
Routing - PLAN CHECK  7/9/2015 FAIL
DetailsCarl D Madsen
Application received  7/8/2015 DONE