GCB-Final | 12/10/2015 | 12/11/2015 | 12/11/2015 | A | PASS |
Tony Young
|
|
|
can you do as early as possilbe? The links between GC and us broke and it should have been done PM 12-10-15,, ok pending trade finals,, issued c of o,,
|
GCB-Energy | 10/16/2015 | 10/16/2015 | 10/16/2015 | P | PASS |
Dave Hannah
|
|
|
Willie ###-####
|
GCB-Framing | 10/14/2015 | 10/15/2015 | 10/15/2015 | A | PASS |
Mike Jordan
|
|
|
Willie ###-####
|
GCB-Framing | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | FAIL |
Mike Jordan
|
|
|
Willie ###-####. Complete all lateral bracing, fire blocl at concealed area ar ceiling in main entry, windows next to fireplace are required to be tempered. A correction notice was issued.
|
GCB-Shearwall | 9/18/2015 | 9/18/2015 | 9/18/2015 | P | PASS |
Phil Shearer
|
|
|
Willie ###-#### - shear nailing insp.
|
GCB-Fndatn/slab ins/fld vent | 8/21/2015 | 8/21/2015 | 8/21/2015 | P | NR |
Dave Hannah
|
|
|
Heron ###-####
|
GCB-Footing | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | PASS |
Tony Young
|
|
|
###-####
|
Plan assigned to (CDM) | 7/17/2015 | 7/17/2015 | 8/11/2015 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 7/21/2015 | | 8/7/2015 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/7/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 8/7/2015 | | DONE |
|
|
|
|
Routing - Mechanical Review | 7/17/2015 | | 7/21/2015 | | PASS |
Troy James
|
|
|
|
Application received | | | 7/16/2015 | | DONE |
|
|
|
via Garden City Web Service
|