CHANGE STATUS TO (FNL) | | | 6/23/2016 | | DONE |
|
|
|
final inspection was done 6/21/16-permit is finaled
|
GCB-Final | 6/21/2016 | 6/21/2016 | 6/21/2016 | P | PASS |
Christina Prado
|
|
|
All inspections complete - inspection added to change status only
|
FIRE-Final Inspection | 5/31/2016 | 6/1/2016 | 6/1/2016 | A | PASS |
Katie Marron
|
|
|
Life Safety Pass. Scope of work complete. Permit Finaled
|
CHANGE STATUS TO (ISS) | | | 5/31/2016 | | DONE |
|
|
|
was finaled w/o fire final by mistake
|
GCB-Final | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PASS |
Dave Hannah
|
|
|
Joe ###-#### - code: 631225*
|
GCB-Final | 5/13/2016 | 5/16/2016 | 5/16/2016 | A | NR |
Jim Sly
|
|
|
Joe ###-#### - code: 631225* Cut off nosing on landing to obtain 11" run. upper 3 tread stairway non compliant.
|
GCB-Final | 3/25/2016 | 3/28/2016 | 3/28/2016 | A | NR |
Jim Sly
|
|
|
Joe ###-#### - code: 631225* Re-built stairway.......Run still approx 1" short......Landings not poured.
|
GCB-Final | 2/25/2016 | 2/26/2016 | 2/26/2016 | A | FAIL |
Mike Jordan
|
|
|
Joe ###-####. North doors require a landings. Stairway to storage above is non compliant. Needs to met IBC 7 inch max rise. 11 inch max run.
|
GCB-Shearwall | 12/17/2015 | 12/18/2015 | 12/18/2015 | A | PASS |
Dave Hannah
|
|
|
Grey ###-#### - Exterior Sheetrock Insp. requested
|
GCB-Framing | 12/3/2015 | 12/3/2015 | 12/3/2015 | P | PASS |
Dave Hannah
|
|
|
Grey ###-####
|
GCB-Shearwall | 11/19/2015 | 11/19/2015 | 11/20/2015 | P | PASS |
Dave Hannah
|
|
|
Shawn ###-####
|
GCB-Framing | 11/16/2015 | 11/17/2015 | 11/17/2015 | A | NR |
Phil Shearer
|
|
|
Shawn ###-####. no plans onsite
|
GCB-Fndatn/slab ins/fld vent | 9/29/2015 | 9/29/2015 | 9/29/2015 | P | PASS |
Dave Hannah
|
|
|
Heron ###-####
|
GCB-Footing | 9/28/2015 | 9/28/2015 | 9/28/2015 | P | PASS |
Jim Sly
|
|
|
Heron ###-####
|
Issue and Courier | | | 9/8/2015 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 7/17/2015 | 7/17/2015 | 9/5/2015 | | DONE |
Carl D Madsen
|
|
|
First review completed.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/7/2015 | | 9/5/2015 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 9/4/2015 | | DONE |
Christina Prado
|
|
|
Received four sets of revised plan sheets marked COVER, 2 of 11, 3 of 11, 4 of 11, 5 of 11, 6 of 11, 7 of 11, 8 of 11, 9 of 11, 10 of 11 & 11 of 11, as well as four sets of structural calcs; Plans & calcs taken to CDM for further review
|
Routing - FIRE | 8/5/2015 | 7/17/2015 | 8/7/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to plans.
|
Routing - PLAN CHECK | | | 8/5/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/5/2015 | | DONE |
Carl D Madsen
|
|
|
|
Application received | | | 7/16/2015 | | DONE |
|
|
|
via Garden City Web Service
|
Routing - Public Works | 7/17/2015 | 7/17/2015 | | | |
Beverly Mountain
|
|
|
|