GCB-Final | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Jim Sly
|
|
|
Ken ###-#### - code: *0604
|
GCB-Energy | 2/4/2016 | 2/4/2016 | 2/4/2016 | P | PASS |
Dave Hannah
|
|
|
Ken ###-#### - code: *0604
|
GCB-Framing | 2/3/2016 | 2/3/2016 | 2/3/2016 | P | PASS |
Dave Hannah
|
|
|
Ken ###-#### - code: *0604 Requested 30min call ahead
|
GCB-Shearwall | 1/8/2016 | 1/8/2016 | 1/11/2016 | P | PASS |
Dave Hannah
|
|
|
Ken ###-####
|
GCB-Shearwall | 1/5/2016 | 1/5/2016 | 1/5/2016 | P | FAIL |
Dave Hannah
|
|
|
Ken ###-#### no city aproved plans on site missing hold downs need an staple equ
|
GCB-Fndatn/slab ins/fld vent | 11/6/2015 | 11/6/2015 | 11/6/2015 | P | PASS |
Dave Hannah
|
|
|
Ken ###-####
|
GCB-Footing | 11/4/2015 | 11/4/2015 | 11/4/2015 | P | PASS |
Tony Young
|
|
|
Ken ###-####
|
Routing - FIRE | 10/28/2015 | 10/28/2015 | 10/28/2015 | | PASS |
Scott Arellano
|
|
|
Fire Department vehicle access evaluated. Fire Hydrant location verified.
|
Plan assigned to (CDM) | 7/23/2015 | 7/23/2015 | 10/22/2015 | | DONE |
Carl D Madsen
|
|
|
First review completed.
|
Routing - PLAN CHECK | 10/22/2015 | | 10/22/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 10/22/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/20/2015 | | DONE |
|
|
|
resubmittals received 3 sheets of A-3, 3 calcs & 1 cover sheet-took to Carl M
|
Routing - PLAN CHECK | 7/23/2015 | | 8/11/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Plan resubmittals requested | | | 8/11/2015 | | DONE |
|
|
|
|
1st review completed | | | 8/11/2015 | | DONE |
|
|
|
|
Application received | | | 7/22/2015 | | DONE |
|
|
|
via Garden City Web Service
|