GCB-Final | 11/9/2015 | 11/9/2015 | 11/9/2015 | P | PEND |
Dave Hannah
|
|
|
Mike ###-#### - access through side gate on north side of house framing ok to cover will still need final after finished
|
Plan assigned to (CDM) | 8/5/2015 | 8/5/2015 | 8/11/2015 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/5/2015 | | 8/7/2015 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/7/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 8/7/2015 | | DONE |
|
|
|
|
Application received | | | 8/5/2015 | | DONE |
|
|
|