GCB-Final | 7/19/2016 | 7/19/2016 | 7/20/2016 | P | PASS |
Jim Sly
|
|
|
permit was finaled by mistake-so had to schedule the fire final-now it needs the building final signed off again so the permit will final out
|
FIRE-Final Inspection | 7/19/2016 | 7/19/2016 | 7/19/2016 | P | PASS |
Katie Marron
|
|
|
Fire Life Safety Pass.
|
CHANGE STATUS TO (ISS) | | | 7/19/2016 | | DONE |
|
|
|
was finaled by mistake-after fire life saftey inspection the building final will need to be called back in so the permit will final out
|
GCB-Final | 7/13/2016 | 7/15/2016 | 7/15/2016 | A | PASS |
Jim Sly
|
|
|
Mike ###-#### - PHASE 2 Structural items OK for Phase 2.
|
GCB-Framing | 6/23/2016 | 6/24/2016 | 6/24/2016 | P | DEFR |
Mike Jordan
|
|
|
Mike ###-#### - PHASE 2 - IT room framing insp... Ran out of time....
|
GCB-Framing | 6/7/2016 | 6/8/2016 | 6/8/2016 | A | PASS |
Mike Jordan
|
|
|
Mike ###-#### - PHASE 2. Interior wood framed walls for two new offices, phase 2 ok.
|
GCB-Final | 5/24/2016 | 5/25/2016 | 5/25/2016 | P | PASS |
Mike Jordan
|
|
|
Mike ###-#### - FINAL FOR TEMP C OF O. Ok to occupy new addition.
|
FIRE-Final Inspection | 5/24/2016 | 5/25/2016 | 5/25/2016 | A | PART |
Jim Page
|
|
|
TCO allowed per conversation with Scott Arellano, in office/cubicle area's of new addition. A fire sprinkler permit will be needed for transition area between new addition and existing building (Area does have upright protection, pendant heads still in place from ceiling removal) Training room in new addition cannot be occupied until head coverage issue is addressed with partition wall construction, heads will be too far off of partition wall with current head layout.
|
GCB-Final | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | NR |
Jim Sly
|
|
|
Mike ###-#### - FINAL FOR TEMP C OF O Need Temp from Fire.
|
GCB-Ceiling Grid | 5/13/2016 | 5/16/2016 | 5/16/2016 | A | PASS |
Jim Sly
|
|
|
Mike ###-####
|
GCB-Courtesy | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | DONE |
Mike Jordan
|
|
|
Mike ###-####. Went over requirements for occupying new area.
|
GCB-Framing | 4/12/2016 | 4/13/2016 | 4/13/2016 | A | PART |
Jim Sly
|
|
|
Mike ###-#### - ceiling framing Hard lids ....OK.
|
GCB-Energy | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Sly
|
|
|
Mike ###-####
|
GCB-Framing | 3/18/2016 | 3/21/2016 | 3/21/2016 | A | PASS |
Jim Sly
|
|
|
framing/cover Brandon ###-#### (if this number does not work then ###-####
|
GCB-Framing | 3/15/2016 | 3/16/2016 | 3/16/2016 | A | NR |
Jim Sly
|
|
|
Brian ###-#### - requested call ahead
|
GCB-Shearwall | 2/29/2016 | 3/1/2016 | 3/1/2016 | A | PASS |
Jim Sly
|
|
|
Mike ###-#### - please inspect roof in addition to shearwall Exterior wall panel and hold down nailing......OK.
|
GCB-Fndatn/slab ins/fld vent | 1/22/2016 | 1/25/2016 | 1/25/2016 | A | PART |
Jim Sly
|
|
|
Mike ###-#### OK pending special inspections, tests and approvals.
|
GCB-Stem wall | 1/22/2016 | 1/25/2016 | 1/25/2016 | A | PASS |
Jim Sly
|
|
|
Mike ###-#### OK pending MTI special inspections, tests and approvals.
|
GCB-Footing | 1/20/2016 | 1/21/2016 | 1/21/2016 | A | PASS |
Jim Sly
|
|
|
Mike ###-#### OK pending MTI special insp, tests, and approvals.
|
Issue and Courier | | | 10/5/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 8/10/2015 | 8/10/2015 | 9/26/2015 | | DONE |
Carl D Madsen
|
|
|
First review completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/25/2015 | | 9/25/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/18/2015 | | 9/25/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | 9/23/2015 | 9/23/2015 | 9/23/2015 | | PASS |
Katie Marron
|
|
|
Updated report attached to plans.
|
Plan resubmittals received | | | 9/23/2015 | | DONE |
|
|
|
resubmittals recieved 4 sets of sheets S2.1 & S4.1 & 4 sets of struc calcs & 1 set comments- took to Carl M
|
Plan resubmittals received | | | 9/21/2015 | | |
|
|
|
resubmittals recieved storm drainage system operation & maintenance plan, comment sheet, 3 sheets of C1.0, C2.0, C3.0, C4.0-took to Carl M
|
Routing Off Site - STRUCTURAL | 9/20/2015 | | 9/21/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/18/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/14/2015 | | 9/18/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | | | 9/14/2015 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 9/10/2015 | | DONE |
|
|
|
resubmittals received 9-4-15-received 5 supplemental structural calcs, 4 review lists, 5 sets of sheet S2.1, S3.1 & S4.1 took to Carl M 9-14-15-Carl M asked me to send it to off site engineering.
|
Routing - FIRE | 8/13/2015 | 8/10/2015 | 8/18/2015 | | FAIL |
Scott Arellano
|
|
|
Awaiting fire flow letter. Report attached to plans.
|
Routing - Plumbing Review | 8/12/2015 | | 8/14/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Mechanical Review | 8/11/2015 | | 8/12/2015 | | PASS |
Troy James
|
|
|
|
Routing - Public Works | 8/10/2015 | 8/10/2015 | 8/11/2015 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 8/6/2015 | | DONE |
|
|
|
via Garden City Web Service
|