Permit Information
Permit NumberGCB15-00121
StatusFinaled
Name Encompass Inc.
Site Address 5100 N SAWYER AVE
Project NameBLD2015-00121
Customer Number 
ePlanReviewNo
Description
""PLAN MODIFICATION TO THE INTERIOR LODING DOCK LEVELER"" Permit for the construction of a new interior loading ramp to serve an existing 24,235 sq. ft. warehouse building with an associated office area. Work to include the addition of a new overhead door on the south wall of the building. This building is fully fire sprinklered for area increase and S-1 occupancy. Modifications to the sprinkler system may be required with the installation of the new overhead door. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final1/22/20161/22/20161/22/2016PPASS
DetailsDave Hannah
Mark ###-####
FIRE-Final Inspection1/21/20161/22/20161/22/2016APASS
DetailsKatie Marron
Fire life safety pass.
FIRE-Conference1/21/20161/21/20161/21/2016ADONE
DetailsKatie Marron
Sprinkler final complete. Verify correct ring installed on hangar at life safety inspection.
GCB-Framing12/4/201512/4/201512/4/2015PPASS
DetailsDave Hannah
Mark ###-#### - requested 2:30p.m. inspection
GCB-Framing11/16/201511/16/201511/16/2015PPASS
DetailsDave Hannah
Paul ###-#### - inspection to look at rebar and walls. Requested 30min call ahead for access
Routing - PLAN CHECK11/5/2015 11/5/2015 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  11/5/2015 DONE
Issue and Courier  11/5/2015 DONE
Plan resubmittals received  11/4/2015 DONE
plan mod received 3 sets of sheet A2, S1.0 & a letter from the architect-took to Carl M
Plan assigned to (CDM)8/18/20158/18/201510/12/2015 DONE
DetailsCarl D Madsen
First review completed
Routing - PLAN CHECK10/12/2015 10/12/2015 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  10/12/2015 DONE
Issue and Courier  10/12/2015 DONE
Plan resubmittals received  10/9/2015 DONE
DetailsChristina Prado
received one set of revised structural calcs, one response letter and three sets revised plan sheets marked A0.0, R1, R2, A1, A2 & S1; Plans stamped and taken to CDM for review
Routing - FIRE9/5/20158/18/20159/9/2015 PASS
DetailsScott Arellano
No comments attached. No field inspection required.
Routing - PLAN CHECK9/9/2015 9/9/2015 FAIL
DetailsCarl D Madsen
1st review completed  9/9/2015 FAIL
Routing - PLAN CHECK  9/5/2015 FAIL
DetailsCarl D Madsen
Application received  8/17/2015 DONE
via Garden City Web Service