GCM-Final | 6/1/2012 | 6/4/2012 | 6/4/2012 | A | PASS |
Dixie Fellows
|
|
|
Mark @ ###-####...final chill and heating pipe tie-ins at river end of motel ok
|
GCM-Rough-in | 5/3/2012 | 5/7/2012 | 5/7/2012 | A | PART |
Dixie Fellows
|
|
|
Mark @ ###-#### As early as possible please...100lb test on hydronics to outside of building ok...ok to cover trench with sand
|
GCM-Rough-in | 5/2/2012 | 5/3/2012 | 5/3/2012 | P | CANC |
Dixie Fellows
|
|
|
Mark @ ###-#### PM Inspection///Cancel per Missy with Garden City
|
GCM-Pressure Test | 4/25/2012 | 4/26/2012 | 4/26/2012 | A | PART |
Jim Johnson
|
|
|
Mark @ ###-#### under ground 60# gas pressure test only test ok
|
GCM-Rough-in | 4/20/2012 | 4/20/2012 | 4/26/2012 | A | DEFR |
Alan Hauser
|
|
|
no reply from contractor
|
GCM-Rough-in | 4/20/2012 | 4/19/2012 | 4/20/2012 | A | FAIL |
Dixie Fellows
|
|
|
Mark @ ###-####....alan and I both called and left a message for mark...no return call..no info about job...no contact at job
|
Application received | | | 4/18/2012 | | DONE |
|
|
|
|