GCM-Final | 9/28/2012 | 9/28/2012 | 9/28/2012 | A | PASS |
Dixie Fellows
|
|
|
gas only for new meter
|
GCM-Pressure Test | 9/27/2012 | 9/28/2012 | 9/28/2012 | A | PASS |
Dixie Fellows
|
|
|
9:00... ###-#### jeff....20lb gas to existing 3/4" pipe going from meter into the building to an existing unit heater
|
GCM-Pressure Test | 9/27/2012 | 9/27/2012 | 9/27/2012 | P | PEND |
Dixie Fellows
|
|
|
Steve @ ###-#### - call for access Jeff @ ###-#### - call for questions PM inspection for today requested....out of time...i called jeff and rescheduled for fri am at 9:00
|
GCM-Final | 9/27/2012 | 9/27/2012 | 9/27/2012 | P | PEND |
Dixie Fellows
|
|
|
Steve @ ###-#### - call for access Jeff @ ###-#### - call for questions PM inspection for today requested...out of time...i called jeff and rescheduled for fri am
|
Application received | | | 9/27/2012 | | DONE |
|
|
|
|