GRD-Final | 4/3/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jeremy Barber
|
GRD-Conference | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | CANC |
Mike Jordan
|
|
|
Please call 1/2 hour in advance Phone #: ###-#### Inspection requested via web by Chris Fuhrman. Cancelled by contractor via phone call.
|
Permit Ready to Issue | | | 10/24/2014 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/24/2014 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 10/24/2014 | | DONE |
|
|
|
|
Routing - FIRE | 10/22/2014 | 10/22/2014 | 10/23/2014 | | PASS |
Craig D. Hanson
|
|
|
No report. project has Fire Flow and is within hydrant spacing.
|
Routing - PLUMBING | 10/22/2014 | | 10/23/2014 | | PASS |
Daryl Spivey
|
|
|
|
Routing PW Drainage | 10/23/2014 | | 10/23/2014 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 10/23/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2014 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 10/21/2014 | | 10/23/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING Land Div | 10/22/2014 | | 10/23/2014 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 10/22/2014 | | 10/22/2014 | | PASS |
Evan Jenkins
|
|
|
SITE PREP INSPECTION REQUIRED PRIOR TO EARTH DISTURBANCE: (Jimmy John's Sandwich Shop - Grading/Drainage) Permit to excavate, grade and compact site earth materials in preparation for a new restaurant submitted under Bld14-02089.
All site work, landscaping,
|
Routing - PLAN CHECK | 10/22/2014 | | 10/22/2014 | | PASS |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 10/22/2014 | | 10/22/2014 | | PASS |
Andrea Tuning
|
|
|
|
Application received | | | 10/20/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 20 2014 9:38AM
|
Intake Approval | | | 10/20/2014 | | PASS |
Tisha Gallop
|
|
|
|