GRD-Final | 5/19/2015 | 5/20/2015 | 5/21/2015 | P | PASS |
Evan Jenkins
|
|
|
Call prior to going Phone #: 2089954228 >> Inspection requested via mobile web by Jeremy Barber PROJECT COPLETE: AS OF NOW, UNABLE TO FINAL OUT PERMIT. I PULLED THE PERMIT OFF SITE. NEXT INSPECTION SHOULD BE ABLE TO FINAL OUT PERMIT. CONDITIONS SATISFIED
|
GRD-Conference | 5/19/2015 | 5/20/2015 | 5/19/2015 | P | CANC |
|
|
|
Call prior to going Phone #: 2089954228 >> Inspection requested via mobile web by Jeremy Barber Inspection cancelled via mobile web on Tuesday, May 19, 2015.
|
Issue PAID IN FULL permit | | | 4/24/2015 | | DONE |
|
|
|
|
Plan assigned to Christina | | | 4/14/2015 | | DONE |
Christina Prado
|
|
|
Took office set to records
|
Routing - PLAN CHECK | 4/15/2015 | | 4/14/2015 | | PASS |
Christina Prado
|
|
|
|
Routing - PLANNING | 4/14/2015 | | 4/14/2015 | | PASS |
Cody Riddle
|
|
|
|
Routing - FIRE | 4/10/2015 | | 4/14/2015 | | PASS |
Scott Arellano
|
|
|
No comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Permit Ready to Issue | | | 4/14/2015 | | DONE |
|
|
|
Need GC form & RP
|
Inspection Record Card-GRD | | | 4/14/2015 | | |
|
|
|
|
Telephone call | | | 4/14/2015 | | DONE |
|
|
|
Left message for Jeremy on fees due as well as RP and GC needed
|
Routing - Erosion and Sediment | 4/8/2015 | | 4/9/2015 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION AND APPROVAL REQUIRED PRIOR TO EARTH DISTURBANCE)
(CAMEL'S BACK PARK) Permit to install 1,927 sq. ft. new concrete slab to serve as future outdoor gym platform as approved by the Public Works Department. No site utilities are included in this scope of work. No buildings are to be constructed or installed under this permit.X-REF ESC15-00389 for Erosion & Sediment Control approval.
|
Plan resubmittals received | | | 4/9/2015 | | DONE |
Christina Prado
|
|
|
Received two revised plan sheets marked 1 of 1 and two revised ESC Narrative documents. Plans inserted with original plans and taken to ESC for review
|
Routing - PUBLIC WORKS | 4/7/2015 | | 4/8/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Drainage | 4/7/2015 | | 4/8/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 4/6/2015 | | 4/7/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PLANNING Land Div | 4/3/2015 | | 4/6/2015 | | PASS |
Todd Tucker
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/3/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 4/3/2015 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/3/2015 | | DONE |
Christina Prado
|
|
|
|
Application received | | 4/3/2015 | | | |
|
|
|
|