GRD-Final | 9/3/2015 | 9/4/2015 | 9/3/2015 | A | PASS |
Jim Storey
|
|
|
Chris Phone #: ###-####
|
PubWorks Occupancy Approval | 8/27/2015 | 8/27/2015 | 8/27/2015 | | DONE |
Tiffany Lowery
|
|
|
|
Issue PAID IN FULL permit | | | 5/19/2015 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 5/19/2015 | | DONE |
|
|
|
|
Routing PW Sewer Design | 5/14/2015 | | 5/15/2015 | | PASS |
Mike Sheppard
|
|
|
Sewer service line is shown on plan. per Mike Shephard.
|
Routing - PLUMBING | 5/15/2015 | | 5/15/2015 | | PASS |
Daryl Spivey
|
|
|
1. install water heater in attic in accordance with the UPC for access and freeze protection.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/15/2015 | | DONE |
|
|
|
need RP, GC and rev cert of val. Recieved Emial on who the RP is and the GC Form, but the
|
Routing - PLAN CHECK | 4/21/2015 | | 5/15/2015 | | PASS |
Brittany Hill
|
|
|
|
Routing - PUBLIC WORKS | 5/14/2015 | | 5/15/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Drainage | 5/14/2015 | | 5/14/2015 | | PASS |
Jason C. Taylor
|
|
|
Project Approved.
|
Routing PW Drainage | 5/13/2015 | | 5/13/2015 | | FAIL |
Jason C. Taylor
|
|
|
Plans not revised as required by Brian.
|
Routing PW Sewer Rating | 5/13/2015 | | 5/13/2015 | | PASS |
Jennifer Bruner
|
|
|
Sewer connection fees will be assessed with BLD unless otherwise requested. Jenn Bruner ###-####
|
Routing PW Street Lights | 4/21/2015 | | 5/12/2015 | | PASS |
Mike D Hedge
|
|
|
No street lights required.
|
Routing PW Sewer Design | 4/21/2015 | | 5/11/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Add notes to connect to existing sewer service line.
|
Routing PW Drainage | 4/21/2015 | | 5/8/2015 | | FAIL |
Brian Murphy
|
|
|
seepage bed needs m well
|
Routing - FIRE | 4/21/2015 | 4/21/2015 | 5/4/2015 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - PLANNING Land Div | 4/21/2015 | | 4/23/2015 | | PASS |
Dave Abo
|
|
|
|
Routing - Design Review | 4/21/2015 | | 4/22/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - Erosion and Sediment | 4/21/2015 | | 4/22/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
1435 sf one story wood framed, pitched roof, wood sided preschool building with asphalt parking and dropoff, seepage bed stormwater system, turf, concrete and mulch play areas and landscaping
|
Routing - PLUMBING | 4/21/2015 | | 4/22/2015 | | FAIL |
Bill VanDegrift
|
|
|
1) provide civil plan showing size and location of sewer and water services and any undergroung rain water piping from the building to the connection of the site system
2) install water heater in attic in accordance with the UPC for access and freeze protection.
|
Routing - Addressing | 4/21/2015 | | 4/21/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 4/21/2015 | | 4/21/2015 | | FAIL |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/21/2015 | | DONE |
|
|
|
|
Intake Approval | | | 4/21/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/21/2015 | | DONE |
|
|
|
|
Application received | | | 4/13/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 13 2015 1:21PM
|