Telephone call | | | 8/12/2015 | | DONE |
|
|
|
Spoke with James and he said he would email me the Cert of Valu with the plumbing value on it. Also informed him that there still needs to be a plumbing permit pulled and attached to this GRD permit
|
Telephone call | | | 8/5/2015 | | DONE |
|
|
|
Left a message for James to touches bases on the value for the plumbing that is going on with this permit. ###-####
|
Telephone call | | | 7/23/2015 | | DONE |
|
|
|
Was informed that Matt is the one to talk to about the PLM. Out of the office until Monday. Left a message that we just need the value for the PLM so that we could add it to this permit
|
GRD-Other | 7/6/2015 | 7/8/2015 | 7/8/2015 | A | CANC |
|
|
|
ELECTRICAL Temp power pole at job trailer needs inspection. Phone #: ###-#### >> Inspection requested via web by Barry Willoughby
|
GRD-Other | 7/6/2015 | 7/6/2015 | 7/7/2015 | P | CANC |
Daryl DeGrange
|
|
|
Request ins. For temporary power pole at job job trailer. Phone #: ###-#### >> Inspection requested via web by Barry Willoughby Inspection cancelled from web by: Barry Willoughby
|
GRD-Other | 7/7/2015 | 7/7/2015 | 7/7/2015 | A | CANC |
|
|
|
Electrical Request temporary power pole inspection for job trailer on Gary Ln. North East corner of Jobsite. Second request. Phone #: ###-#### >> Inspection requested via web by Barry Willoughby
|
Issue PAID IN FULL permit | | | 6/22/2015 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 6/22/2015 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 6/11/2015 | | 6/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Street Lights | 6/11/2015 | | 6/12/2015 | | PASS |
Mike D Hedge
|
|
|
|
Permit Ready to Issue | | | 6/12/2015 | | DONE |
|
|
|
Need Revised Cert of Valu, GC Form and RP// all requirements met 6-17-15 KRS
|
Routing PW Drainage | 6/10/2015 | | 6/10/2015 | | PASS |
Jason C. Taylor
|
|
|
GRADING ONLY. Drainage will be approved at a later date due to required review and revisons of grading area. Jason Taylor ###-####.
|
Routing - PUBLIC WORKS | 5/26/2015 | | 5/28/2015 | | FAIL |
Jennifer Bruner
|
|
|
See PW Drainage and Street Lighting.
|
Routing PW Street Lights | 5/27/2015 | | 5/28/2015 | | FAIL |
Mike D Hedge
|
|
|
See Changemarks in E-Plan Review.
|
Routing PW Drainage | 5/27/2015 | | 5/28/2015 | | FAIL |
Jason C. Taylor
|
|
|
Plans need revised. Punchlist will be sent ot applicant when completed. Jason Taylor ###-####
|
Routing - FIRE | 5/7/2015 | 5/7/2015 | 5/11/2015 | | PASS |
Scott Arellano
|
|
|
Approved. Any traffic calming devices (speed bumps) must be approved by the Fire Chief.
|
Routing - Erosion and Sediment | 5/7/2015 | | 5/11/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Project Constists of Pave existing dirt lot, work to include asphalt paving, landscaping, site lighting improvements, & storm water management.
|
Routing - PUBLIC WORKS | 5/7/2015 | | 5/8/2015 | | FAIL |
Jennifer Bruner
|
|
|
See PW Drainage, Street Lighting,
|
Routing - Design Review | 5/7/2015 | | 5/8/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing PW Drainage | 5/7/2015 | | 5/8/2015 | | FAIL |
Jason C. Taylor
|
|
|
Requested paper plans for review. Jason Taylor ###-####.
|
Routing PW Street Lights | 5/7/2015 | | 5/8/2015 | | FAIL |
Mike D Hedge
|
|
|
See Mark Ups
|
Routing PW Sewer Design | 5/7/2015 | | 5/8/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
**SEPARATE APPROVAL REQUIRED** Submit sewer plans to public works review and approval per the sewer extension policy.
|
Routing PW Solid Waste | 5/7/2015 | | 5/8/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - Addressing | 5/7/2015 | | 5/7/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PLUMBING | 5/7/2015 | | 5/7/2015 | | PASS |
Daryl Spivey
|
|
|
|
Routing - PLANNING Land Div | 5/7/2015 | | 5/7/2015 | | PASS |
Todd Tucker
|
|
|
|
Intake Approval | | | 5/7/2015 | | PASS |
|
|
|
|
Intake Approval | | | 4/30/2015 | | FAIL |
|
|
|
Need Planning approval, united water flow sheet and verify site lighting.
|
Application received | | | 4/20/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 20 2015 3:55PM
|
Plan assigned to (BLH)Brittany | 5/7/2015 | | | | |
Brittany Hill
|
|
|
|