GRD-Final | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | FAIL |
Jim Storey
|
|
|
Per Daryl DeGrange ELE16-002473 was also part of the site lighting need fire sign off
|
GRD-Final | 1/23/2019 | 1/23/2019 | 1/23/2019 | P | FAIL |
Jim Storey
|
|
|
need ele permit and signoff/ need fire final signoff// no contact info. provided.
|
PubWorks Occupancy Approval | 11/15/2016 | 11/15/2016 | 11/15/2016 | | DONE |
Tiffany Lowery
|
|
|
|
(F) Reprint permit | | | 6/9/2016 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/9/2016 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 5/9/2016 | | DONE |
|
|
|
|
Plan assigned to Christina | 3/24/2016 | | 5/5/2016 | | DONE |
Christina Prado
|
|
|
|
Routing PW Drainage | 4/22/2016 | | 5/5/2016 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/2016 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 5/5/2016 | | DONE |
|
|
|
***all requirments met 5-5-16 /CEV
Needs; GC Form, Revised Cert of Value
|
Routing - PLAN CHECK | 3/24/2016 | | 4/19/2016 | | PEND |
Christina Prado
|
|
|
Pending PW Drainage approval
|
Routing PW Street Lights | 3/24/2016 | | 4/19/2016 | | PASS |
Tom Marshall
|
|
|
Per eReview approval
|
Routing PW Drainage | 3/24/2016 | | 4/18/2016 | | FAIL |
Brian Murphy
|
|
|
plan never recieved in e plan needs o and m revision and agreement
|
Routing - PLANNING | 3/24/2016 | | 4/4/2016 | | PASS |
Todd Tucker
|
|
|
ros16-00024
|
Routing - PLANNING Land Div | 3/24/2016 | | 4/4/2016 | | PASS |
Todd Tucker
|
|
|
Per eplan approval
|
Routing - FIRE | 3/24/2016 | 3/24/2016 | 3/28/2016 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD access and water availability. All new hydrants shall be installed prior to the storage/framing of combustible materials on site.
|
Routing - PLUMBING | 3/24/2016 | | 3/28/2016 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Erosion and Sediment | 3/24/2016 | | 3/25/2016 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
(CITADEL STORAGE) - Grading permit to excavate, grade and pave an existing dirt lot in preparation for a new fully enclosed self-storage facility. Work to include asphalt paving, landscaping, Curbing, striping, site lighting improvements, & storm water management
|
Routing - Addressing | 3/24/2016 | | 3/24/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/24/2016 | | 3/24/2016 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 3/24/2016 | | 3/24/2016 | | PASS |
Andrea Tuning
|
|
|
drh16-00042
|
Plans ACCEPTED BY PLAN TECH | | | 3/24/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/24/2016 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/24/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 3/23/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 23 2016 9:00AM
|