Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberGRD16-00084
StatusFinaled
Name ESI
Site Address 12142 W JOPLIN RD
Project NameFire Training
Customer NumberCUP16-00062
ePlanReviewYes
Description
(BOISE FIRE DEPARTMENT - Training Facilities) - Grading permit to excavate, grade and compact site earth materials in preparation for 4 new shell building to be constructed under BLD16-04077, BLD16-04079, BLD16-04271 & BLD16-04428. All work to be performed as approved by the Public Works Department and Planning & Zoning Department under CUP16-00062. Underground utilities only, no buildings or footings are allowed to be constructed under this permit. (C_P)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  1/18/2019 DONE
Per passing final inspection 5/31/18 by Jim Sly
GRD-Conference5/30/20185/31/20185/31/2018ACANC
DetailsJim Sly
Nick Phone #: ###-####
GRD-Final5/31/20185/31/20185/31/2018ADONE
DetailsTiffany Lowery
PubWorks Occupancy Approval5/31/20185/31/20185/31/2018 DONE
DetailsTiffany Lowery
CHANGE STATUS TO (ISS)  4/4/2018 DONE
DetailsRita DeYoung
Needs Public Works approval, 5/30/18 Per Tiffany Lowery PW approvals are complete.
GRD-Final3/29/20183/29/20183/30/2018PPASS
DetailsTroy Cobbley
Life safety passed. The fire dept is going to address the bollards at the fire hydrants and the gate width/access issues per Assistant Chief Ron.

Phone #: ###-#### Inspection requested via web by Chris Palmer
FIRE-Final Inspection3/29/20183/29/20183/30/2018PPASS
DetailsTroy Cobbley
Life safety passed. The fire dept is going to address the bollards at the fire hydrants and the gate width/access issues per Assistant Chief Ron.

Phone #: ###-#### Inspection requested via web by Chris Palmer
FIRE-Final Inspection3/28/20183/29/20183/29/2018PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection3/27/20183/28/20183/28/2018AFAIL
DetailsTroy Cobbley
No city approved plans or small documents on site. No inspection performed.

Phone #: ###-#### Inspection requested via web by Chris Palmer
Issue PAID IN FULL permit  3/28/2017 DONE
Inspection Record Card-GRD  3/28/2017 DONE
DetailsChristina Prado
Routing - PUBLIC WORKS GRADING1/11/2017 1/11/2017 PASS
DetailsJim Wyllie
Routing PW Drainage1/6/2017 1/10/2017 PASS
DetailsJim Wyllie
Per ePlan
Routing PW Sewer Design1/6/2017 1/10/2017 PASS
DetailsKyle S. Rosenmeyer
PLANS/APPL TAKEN TO FRONT DESK  1/10/2017 DONE
DetailsChristina Prado
Permit Ready to Issue  1/10/2017 DONE
need GC and Rev Cert of val
Plan assigned to Christina11/22/2016 1/10/2017 DONE
DetailsChristina Prado
Routing - PLAN CHECK11/22/2016 1/10/2017 PASS
DetailsChristina Prado
Routing - FIRE12/12/201612/12/201612/12/2016 PASS
DetailsKatie Marron
Received Letter from Fire Chief, 'OK' with current design. Letter attached to case.
Routing PW Street Lights11/22/2016 12/1/2016 PASS
DetailsTom Marshall
Routing - PLANNING11/22/2016 11/29/2016 PASS
DetailsLeon Letson
CUP16-00062
Routing - PLANNING Land Div11/22/2016 11/29/2016 PASS
DetailsLeon Letson
Routing PW Solid Waste11/22/2016 11/28/2016 PASS
DetailsEvan Carpenter
Solid waste OK as planned.
Routing PW Sewer Design11/22/2016 11/28/2016 FAIL
DetailsKyle S. Rosenmeyer
Show angle of core drill into manhole 589F. Provide kor-n-seal boot or equivilant product to ensure water tight seal. Contact Boise Public Works 48 hours prior to manhole work to obtain tap permit and schedule inspection.

Change manhole label from 589F1 to a number unrelated to the Boise Sewer manholes nearby (to avoid confusion).
Routing - Erosion and Sediment11/22/2016 11/25/2016 PASS
DetailsAndy J. Long
SWPPP submitted and approved. Valid PD, RP to be designated . Site preparation inspeciton required, call ###-####
Routing PW Environmental11/22/2016 11/25/2016 PASS
DetailsRick Christenson
Routing - FIRE11/22/201611/22/201611/23/2016 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing - PLUMBING11/22/2016 11/23/2016 PASS
DetailsBill VanDegrift
Plans ACCEPTED BY PLAN TECH  11/22/2016 DONE
Intake Approval  11/22/2016 PASS
Recd Pcfee & Taken To Pln CK  11/22/2016 DONE
Routing - Addressing11/22/2016 11/22/2016 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS11/22/2016 11/22/2016 PASS
DetailsRachael Beierle
Application received  11/7/2016 DONE
Application submitted via PDS Online on Nov 7 2016 3:45PM
Routing PW Drainage11/22/2016   FAIL
DetailsBrian Murphy
need 3 feet and size plus apdx j