GRD-Final | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | DONE |
Tiffany Lowery
|
|
|
|
PubWorks Occupancy Approval | 2/12/2019 | 2/12/2019 | 2/12/2019 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 2/7/2019 | 2/8/2019 | 2/8/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Nate Phone #: ###-####
|
Inspection Record Card-GRD | | | 2/7/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/31/2017 | | DONE |
|
|
|
|
Routing PW Sewer Design | 2/16/2017 | | 2/27/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PLAN CHECK | 2/16/2017 | | 2/27/2017 | | PASS |
Candy A. Nichols
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/27/2017 | | DONE |
|
|
|
ALL MET NEED RP, GC & rev cert of val
|
Plan assigned to (CAN) Candy | 12/16/2016 | | 2/27/2017 | | DONE |
Candy A. Nichols
|
|
|
|
Meeting | | | 2/22/2017 | | DONE |
|
|
|
Appendix J taken to Brian Murphy
|
Routing - FIRE | 2/16/2017 | 2/16/2017 | 2/16/2017 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing PW Sewer Design | 1/24/2017 | | 2/8/2017 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Label manhole 861C3A.
Use precast base, and contact Boise Public Works 48 hours prior to installation in W. Irving St. Contractor shall CCTV sewer line up and downstream of new manhole and provide records to Boise Public Works.
|
Routing PW Drainage | 1/24/2017 | | 2/7/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 1/24/2017 | 1/24/2017 | 1/25/2017 | | FAIL |
Katie Marron
|
|
|
FD Access not approved. Revised report attached to case and emailed to applicant.
|
Plan resubmittals received | | | 1/24/2017 | | DONE |
|
|
|
e plan review resubmittals received
|
Plan resubmittals received | | | 1/24/2017 | | DONE |
|
|
|
|
Plan assigned to (CAN) Candy | 1/24/2017 | | 1/24/2017 | | DONE |
Candy A. Nichols
|
|
|
some of the drawings didn't uplaod correctly so i failed in E Plan Review so the customer could re-upload them
|
Plan resubmittals received | | | 1/24/2017 | | DONE |
|
|
|
2nd resubmit for today-problem was fixed so sent it for plan review
|
Routing - PLAN CHECK | 12/16/2016 | | 1/6/2017 | | FAIL |
Candy A. Nichols
|
|
|
sent back to applicant for corrections
|
Routing - PLANNING | 12/16/2016 | | 1/6/2017 | | PASS |
Sarah Schafer
|
|
|
Approved
|
Routing PW Drainage | 12/16/2016 | | 1/4/2017 | | FAIL |
Brian Murphy
|
|
|
NEEDStruck wash not to goto sw,apdx j and soil in swale
|
Routing PW Sewer Design | 12/16/2016 | | 12/29/2016 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Label Manhole SSMH 861C3. Core manhole and install 8" sewer line with Kor-N-Seal boot to ensure watertight connection. Channel manhole based to create smooth flowline (flow direction is West). Contact Boise Public Works 48 hours prior to performing sewer work in W. Irving Street to obtain a tap permit and schedule inspection. Delineate Public/Private sewer on Plan/Profile view at property line.
|
Routing - FIRE | 12/16/2016 | 12/16/2016 | 12/19/2016 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing PW Street Lights | 12/16/2016 | | 12/19/2016 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING Land Div | 12/16/2016 | | 12/19/2016 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 12/16/2016 | | 12/19/2016 | | PASS |
Andy J. Long
|
|
|
ESC site map and narrative approved. Valid PD and RP designated. Site preparation inspection required.
|
Plans ACCEPTED BY PLAN TECH | | | 12/16/2016 | | DONE |
|
|
|
|
Intake Approval | | | 12/16/2016 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/16/2016 | | DONE |
|
|
|
|
Routing - Addressing | 12/16/2016 | | 12/16/2016 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/16/2016 | | 12/16/2016 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 12/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 15 2016 9:44AM
|