GRD-Final | 10/30/2018 | 10/30/2018 | 10/30/2018 | P | PASS |
Dave Hannah
|
|
|
Jan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/21/2017 | | DONE |
|
|
|
|
Routing PW Flood Plain | 6/8/2017 | | 7/17/2017 | | PASS |
Jim Wyllie
|
|
|
no review required. JCT
|
Permit Ready to Issue | | | 7/17/2017 | | DONE |
|
|
|
met
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 7/17/2017 | | DONE |
|
|
|
made RDY by mistake before i sent to front desk and signed off
|
Plan assigned to (CAN) Candy | 6/7/2017 | | 7/17/2017 | | DONE |
Candy A. Nichols
|
|
|
|
Routing - PLAN CHECK | 6/7/2017 | | 7/17/2017 | | PASS |
Candy A. Nichols
|
|
|
|
Routing PW Sewer Design | 6/12/2017 | | 7/13/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Drainage | 7/13/2017 | | 7/13/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 6/29/2017 | 6/29/2017 | 7/3/2017 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing PW Solid Waste | 6/8/2017 | | 6/15/2017 | | PASS |
Evan Carpenter
|
|
|
No dumpster locations shown on plans and so none approved.
|
Routing PW Drainage | 6/8/2017 | | 6/13/2017 | | FAIL |
Brian Murphy
|
|
|
NEEDAPDX J , M WELL IN SEEPAGE BED PERC TESTS ECT
|
Routing - PLANNING | 6/7/2017 | | 6/12/2017 | | PASS |
Cody Riddle
|
|
|
|
Routing - Erosion and Sediment | 6/7/2017 | | 6/9/2017 | | PASS |
Andy J. Long
|
|
|
SWPPP with narrative and site map approved. Valid PD and RP desiganted. Site preparation inspection required, call ###-####
|
Routing PW Street Lights | 6/8/2017 | | 6/9/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - FIRE | 6/7/2017 | 6/7/2017 | 6/8/2017 | | FAIL |
Katie Marron
|
|
|
report attached to case and emailed to architect.
|
Routing - Addressing | 6/7/2017 | | 6/8/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/7/2017 | | 6/8/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING Land Div | 6/7/2017 | | 6/8/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Design Review | 6/7/2017 | | 6/8/2017 | | PASS |
Katelyn Menuge
|
|
|
No Review Required
|
Plans ACCEPTED BY PLAN TECH | | | 6/7/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/7/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/7/2017 | | DONE |
|
|
|
ESC fees paid
|
Intake Approval | | | 6/6/2017 | | FAIL |
|
|
|
still need to upload drawings individually
|
Intake Approval | | | 5/1/2017 | | FAIL |
|
|
|
need to upload drawings individually
|
Application received | | | 4/27/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 27 2017 3:09PM
|