GRD-Final | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Jim Sly
|
|
|
Buildings and parking areas complete and finaled. Final....OK.
|
GRD-Final | 1/23/2019 | 1/23/2019 | 1/23/2019 | A | DEFR |
Jim Sly
|
|
|
Direct to Public Works....
|
GRD-Final | 6/6/2018 | 6/6/2018 | 6/6/2018 | A | DONE |
Tiffany Lowery
|
|
|
Received engineer letter 06/04/18 and easement agreement 06/01/18
|
PubWorks Occupancy Approval | 6/6/2018 | 6/6/2018 | 6/6/2018 | | DONE |
Tiffany Lowery
|
|
|
|
Issue PAID IN FULL permit | | | 7/25/2017 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 5/26/2017 | | 7/14/2017 | | DONE |
Tisha Gallop
|
|
|
rough grading
|
Routing PW Drainage | 7/14/2017 | | 7/14/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 7/14/2017 | | 7/14/2017 | | PASS |
Rachael Beierle
|
|
|
rough grading only. No utilities until GRD comes through.
|
Plan Reviewer's activity | | | 7/14/2017 | | DONE |
|
|
|
Per Brian Murphys request re-route to public works
|
Routing - FRONT DESK | 7/14/2017 | | 7/14/2017 | | PASS |
Tisha Gallop
|
|
|
all applicable department reviews passed. One copy taken to records
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/14/2017 | | DONE |
|
|
|
need GC form
|
Inspection Record Card-GRD | | | 7/14/2017 | | DONE |
|
|
|
|
Telephone call | | | 7/14/2017 | | DONE |
|
|
|
Left a message for Jim informing him this permit is ready to be picked up, stated the fee amount and that a GC Form is needed.
|
Routing - FRONT DESK | 6/7/2017 | | 6/9/2017 | | FAIL |
Tisha Gallop
|
|
|
Tisha
Pending drainage & street light approval. Called application to advise
|
Routing - Erosion and Sediment | 6/6/2017 | | 6/7/2017 | | PASS |
Melissa Jannusch
|
|
|
Plan approved.
|
Routing - PUBLIC WORKS | 5/26/2017 | | 6/6/2017 | | FAIL |
Rachael Beierle
|
|
|
|
Routing PW Street Lights | 6/6/2017 | | 6/6/2017 | | PASS |
Tom Marshall
|
|
|
No street light plan
|
Routing PW Drainage | 5/26/2017 | | 5/30/2017 | | FAIL |
Brian Murphy
|
|
|
NEEDS CANAL AGREEMENT
|
Intake Approval | | | 5/26/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/26/2017 | | DONE |
|
|
|
|
Routing - Addressing | 5/26/2017 | | 5/26/2017 | | PASS |
Laura Hunter
|
|
|
Changed address to 7455 W Sift Ln due to no access to facility from N Cole Rd
|
Routing PW Sewer Rating | 5/26/2017 | | 5/26/2017 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT. NO FEES AT THIS TIME. GRADING PERMIT ONLY.
|
Application received | | 5/23/2017 | | | |
|
|
|
|