Permit Information
Permit NumberGRD17-00059
StatusFinaled
Name CANNING CONSTRUCTION INC
Site Address 9417 W EMERALD ST
Project NameVisions
Customer NumberDRH17-00392
ePlanReviewYes
Description
(Visions Bld Parking Expansion) *** PLAN MODIFICATION 11/6/17 to add Pole Lighting to scope of work C_P *** Permit to excavate, grade, and pave a parking lot per engineered plans on file as approved by Public Works Department. Install curbing and striping as noted on plans. Electrical permit required for site lighting. No buildings are to be constructed or installed under this permit. Reference DRH17-00392 for planning/zoning approval // (CAN)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  7/20/2018 DONE
after talking with Christina-we are doc finaling this grading permit because all inspections are done
PubWorks Occupancy Approval3/26/20183/26/20183/26/2018 DONE
DetailsTiffany Lowery
Bonding agreement received 03/23/2018
CHANGE STATUS TO (ISS)  3/7/2018 DONE
changed final to issue-was finaled by mistake-see notes in blg final-need blg final and PW works
GRD-Final12/22/201712/22/201712/22/2017PPASS
DetailsMike Jordan
Greg Pitassi Phone #: ###-####. Will be of for perm final when public works signs perm. Reviewed all special inspection reports. ok
PubWorks Temp Occupancy Appr12/22/201712/22/201712/22/2017 DONE
DetailsTiffany Lowery
GRD-Final12/21/201712/21/201712/21/2017PNR
DetailsMike Jordan
Call when you get there please // Greg Phone #: ###-####.
CHANGE STATUS TO (ISS)  12/21/2017 DONE
should not be finaled
FIRE-Final Inspection12/18/201712/18/201712/18/2017PPASS
DetailsTroy Cobbley
Life safety passed

Jeff Phone #: ###-####
Routing PW Street Lights11/6/2017 11/7/2017 PASS
DetailsTom Marshall
PLANS/APPL TAKEN TO FRONT DESK  11/7/2017 DONE
DetailsChristina Prado
Permit Ready to Issue  11/7/2017 DONE
CHANGE STATUS TO (ISS)  11/7/2017 DONE
Plan assigned to (LEG) Tisha11/6/2017 11/7/2017 DONE
DetailsTisha Gallop
plan mod for pole lighting. PW & planning
Routing - FRONT DESK11/6/2017 11/6/2017 PASS
DetailsTisha Gallop
plan mod for pole lighting
Routing - Design Review11/6/2017 11/6/2017 PASS
DetailsKatelyn Menuge
Routing - PUBLIC WORKS11/6/2017 11/6/2017 PASS
DetailsMorgan Webb
plan mod for pole lighting
Routing PW Drainage11/6/2017 11/6/2017 PASS
DetailsJason C. Taylor
Plan Modification Accepted  11/6/2017 DONE
plan modification started for modification to pole lighting
Issue PAID IN FULL permit  10/11/2017 DONE
Inspection Record Card-GRD  10/11/2017 DONE
Routing PW Drainage10/4/2017 10/10/2017 PASS
DetailsJason C. Taylor
PLANS/APPL TAKEN TO FRONT DESK  10/10/2017 DONE
Permit Ready to Issue  10/10/2017 DONE
ALL MET-Need
RP-MET
GC-MET
Rev Cert of Val-MET
Plan assigned to (CAN) Candy9/29/2017 10/10/2017 DONE
DetailsCandy A. Nichols
Routing - PLAN CHECK9/11/2017 10/10/2017 PASS
DetailsCandy A. Nichols
Routing - PUBLIC WORKS9/29/2017 10/10/2017 PASS
DetailsRachael Beierle
Routing - Design Review9/29/2017 9/29/2017 PASS
DetailsKatelyn Menuge
Routing - FIRE9/11/20179/11/20179/20/2017 PASS
DetailsScott Arellano
No comments attached. Scope of work does not affect existing fire department vehicle access.
Routing PW Sewer Design9/11/2017 9/14/2017 PASS
DetailsKyle S. Rosenmeyer
Routing - Erosion and Sediment9/11/2017 9/14/2017 PASS
DetailsAndy J. Long
ESC plan approved.Certified ESC Responsible Person designated.
Routing PW Drainage9/11/2017 9/12/2017 FAIL
DetailsJason C. Taylor
See changemarks in ePlan. JCT
Routing PW Solid Waste9/11/2017 9/12/2017 PASS
DetailsEvan Carpenter
Routing PW Street Lights9/11/2017 9/11/2017 PASS
DetailsTom Marshall
Routing PW Sewer Rating9/11/2017 9/11/2017 PASS
DetailsMorgan Webb
Plans ACCEPTED BY PLAN TECH  9/11/2017 DONE
Intake Approval  9/11/2017 PASS
Routing - Design Review9/11/2017 9/11/2017 FAIL
DetailsKatelyn Menuge
See architectural and civil site plans for required corrections.
Routing - Addressing9/11/2017 9/11/2017 PASS
DetailsDoug Chausow
Recd Pcfee & Taken To Pln CK  9/9/2017 DONE
Application received  9/8/2017 DONE
Application submitted via PDS Online on Sep 8 2017 11:27AM