Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberGRD17-00085
StatusIssued
Name CLEARWATER LANDSCAPE AND IRRIGATION
Site Address 310 S HILTON ST
Project NameFranklin Park
Customer Number 
ePlanReviewNo
Description
(FRANKLIN PARK - Green-Up) To conduct excavation of approximately 1900 cubic yards of earth to repair exitings landscaping, install walking path, and repair and restripe parking area. All work is to be done as approved by the City of Boise, Public Works, Planning & Zoning, and Erosion departments. No structures or building construction is allowed under this permit. ESC17-01701 is to be issued with this permit. //leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GRD-Final4/10/20194/17/20194/17/2019PPASS
DetailsAndy J. Long
Old permit that needs to be closed out Phone #: ###-#### Inspection requested via web by David Snow
Reopen Permit (ISS)  4/17/2019 DONE
needs inspection with PW and GRD final by building inspector
Telephone call  4/17/2019 DONE
Spoke with David informing him that for a final in specation on a GRD he would need to call us because it doesn't get assinged to anyone when done online and that he would need to have a PW inspection completed first
Issue PAID IN FULL permit  1/10/2018 DONE
Routing - PLAN CHECK1/8/2018 1/9/2018 PASS
DetailsTisha Gallop
1st review completed  1/9/2018 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/9/2018 DONE
Permit Ready to Issue  1/9/2018 DONE
Need:
GC form
Inspection Record Card-GRD  1/9/2018 DONE
Telephone call  1/9/2018 DONE
called David to let know permit is ready and how much is owed-also taht we need to know who the GC and the GC form
Plan assigned to (LEG) Tisha12/21/2017 1/9/2018 DONE
DetailsTisha Gallop
Routing - PUBLIC WORKS12/22/2017 1/8/2018 PASS
DetailsRachael Beierle
Routing - PLANNING1/8/2018 1/8/2018 PASS
DetailsCody Riddle
The applicant/owner shall obtain approval from ACHD for any work in the ROW.
Routing PW Drainage1/4/2018 1/5/2018 PASS
DetailsBrian Murphy
rough grading only ACHD PONDS NO INSPECTIONS NEEDED
Routing PW Street Lights1/3/2018 1/4/2018 PASS
DetailsTom Marshall
Routing PW Solid Waste1/2/2018 1/2/2018 PASS
DetailsEvan Carpenter
Routing PW Sewer Design12/26/2017 12/26/2017 PASS
DetailsMike Sheppard
Routing - Erosion and Sediment12/22/2017 12/22/2017 PASS
DetailsTisha Gallop
see activity in ESC17-01701
Intake Approval  12/21/2017 PASS
Plans ACCEPTED BY PLAN TECH  12/21/2017 DONE
Recd Pcfee & Taken To Pln CK  12/21/2017 DONE
Application received 12/19/2017   
Plan assigned to (BLH)Brittany12/22/2017    
DetailsBrittany Hill