Permit Information
Permit NumberGRD18-00014
StatusIssued
Name LM CONSTRUCTION CO LLC
Site Address 8485 S FEDERAL WAY
Project NameLM CONSTRUCTION
Customer Number 
ePlanReviewYes
Description
(LM CONSTRUCTION - GRADING) Grading permit to excavate, grade and compact site earth materials in preparation for a new shell building to be constructed under a future building permit, filed under BLD18-00596. All work to be performed as approved by the Public Works Department and Planning & Zoning Department under DRH17-00143. Scope of work includes underground utilities only. No buildings or footings are allowed to be constructed under this permit. ESC17-01488 is to be issued with this permit.//leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection1/10/20191/11/20191/14/2019ACANC
DetailsJim Page
Signature not required for life fire safety per permit details, this request is cancelled.

Michael Pearson On Site Superintendent Phone #: ###-#### Inspection requested via web by Larry Monkarsh
GRD-Final1/10/20191/11/20191/11/2019ANR
DetailsJim Storey
Michael Pearson On Site Superintendent Phone #: ###-#### Inspection requested via web by Larry Monkarsh
Meeting  1/11/2019 DONE
per Daryl DeGrange no underground electrical work will be done during grading phase of this project. Changed requried signature for electrical to No.
Issue PAID IN FULL permit  4/5/2018 DONE
Inspection Record Card-GRD  4/5/2018 DONE
Plan assigned to (LEG) Tisha2/13/2018 3/2/2018 DONE
DetailsTisha Gallop
Routing PW Street Lights3/2/2018 3/2/2018 PASS
DetailsTom Marshall
PLANS/APPL TAKEN TO FRONT DESK  3/2/2018 DONE
DetailsChristina Prado
Permit Ready to Issue  3/2/2018 DONE
NEED
RP
GC FORM
REVISED VALUE
Routing PW Drainage3/1/2018 3/1/2018 PASS
DetailsBrian Murphy
1st review completed  2/23/2018 FAIL
pending PW Drainage, PW street lights
Routing PW Sewer Design2/14/2018 2/23/2018 PASS
DetailsMike Sheppard
Routing - FRONT DESK2/13/2018 2/23/2018 PASS
DetailsTisha Gallop
Routing PW Street Lights2/14/2018 2/21/2018 FAIL
DetailsTom Marshall
Routing PW Drainage2/14/2018 2/21/2018 FAIL
DetailsBrian Murphy
need variance
Routing - FIRE2/13/20182/13/20182/20/2018 PASS
DetailsErika Akin
No comments attached. Site access, hydrants, aerial access and radii IFC compliant. Full review to be completed with building permit.
Routing - Erosion and Sediment2/13/2018 2/20/2018 PASS
DetailsMichael Zawacki
ref ESC17-01488
RP & site inspection required before any disturbance
Routing PW Solid Waste2/14/2018 2/16/2018 PASS
DetailsEvan Carpenter
Routing - PLUMBING2/13/2018 2/15/2018 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing PW Environmental2/14/2018 2/15/2018 PASS
DetailsRick Christenson
Routing - PUBLIC WORKS2/13/2018 2/14/2018 PASS
DetailsRachael Beierle
Routing - Addressing2/13/2018 2/14/2018 PASS
DetailsDoug Chausow
Application received  2/13/2018 DONE
Application submitted via PDS Online on Feb 13 2018 2:23PM
Intake Approval  2/13/2018 PASS
Plans ACCEPTED BY PLAN TECH  2/13/2018 DONE
Routing - Design Review2/13/2018 2/13/2018 PASS
DetailsKatelyn Menuge
Grading Okay. Drainage swales shall not preclude required trees. A cross-access agreement will need to be submitted for review for the northern driveway, and then recorded, prior to building permit submittal. DRH17-00143 Katelyn