Description
(Salvation Army) - Grading permit to excavate, grade and compact site earth materials in preparation for a new shell building to be constructed under BLD17-04447 . All work to be performed as approved by the Public Works Department and Planning & Zoning Department under DRH18-00085 . Separate (electrical and/or pluming) permit is required for site underground utilities. No buildings or footings are allowed to be constructed under this permit. (CAN)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GRD-Final9/24/20199/25/20199/25/2019APASS
DetailsMike Jordan
Jim Phone #: ###-####
CHANGE STATUS TO (ISS)  9/24/2019 DONE
not sure why closed out, no pw inspection or final
FIRE-Final Inspection9/23/20199/23/20199/23/2019PPASS
DetailsTroy Cobbley
Life safety passed. The review and inspection for this permit was performed under the BLD permits. Jim Phone #: ###-####
PLANS/APPL TAKEN TO FRONT DESK  4/20/2018 DONE
Permit Ready to Issue  4/20/2018 DONE
Need
GC Form
Revised Cert of Value
Issue PAID IN FULL permit  4/20/2018 DONE
Inspection Record Card-GRD  4/20/2018 DONE
Routing - FRONT DESK4/10/2018 4/20/2018 PASS
DetailsCandy A. Nichols
Plan assigned to (CAN) Candy4/10/2018 4/20/2018 DONE
DetailsCandy A. Nichols
Routing - Design Review4/17/2018 4/19/2018 PASS
DetailsAndrea Tuning
Telephone call  4/19/2018 DONE
emailed Corinne that we received the hold harmless letter but still need corrections for the PW Sewer Design plan reviewer. I also let her know that the GC will need to get us the 302 & 306 forms once the permit is made ready
Routing PW Sewer Design4/19/2018 4/19/2018 PASS
DetailsDeAnn Brown
Routing - Addressing4/17/2018 4/17/2018 PASS
DetailsDoug Chausow
Routing PW Sewer Design4/17/2018 4/17/2018 PASS
DetailsDeAnn Brown
Routing - Erosion and Sediment4/10/2018 4/13/2018 PASS
DetailsMichael Zawacki
Prebid SWPPP narrative submitted. Projected needs valid RP and site inspection prior to start.
Routing - FIRE4/10/20184/10/20184/11/2018 PASS
DetailsErika Akin
Reviewed under BLD17-04447
Routing - PLUMBING4/10/2018 4/11/2018 PASS
DetailsBill VanDegrift
Routing PW Drainage4/10/2018 4/10/2018 PASS
DetailsBrian Murphy
Routing PW Street Lights4/10/2018 4/10/2018 PASS
DetailsTom Marshall
Routing PW Sewer Design4/10/2018 4/10/2018 PASS
DetailsDeAnn Brown
Routing - Design Review4/10/2018 4/10/2018 FAIL
DetailsAndrea Tuning
Complete a record of survey for a lot consolidation prior to issuance of building permits.
Vacate the drainage easement located on the site from the subdivision plat prior to issuance of building permits.
Install one Class II tree with low growing shrubs or groundcover within each of the required interior/terminal planters. This will require the relocation of one tree and the addition of four new trees.
Prior to submitting for a building permit, the applicant will be required to clearly identify the location of all mechanical units and how they will be screened from public view. All mechanical units shall provide full height screening.
Routing - Addressing4/10/2018 4/10/2018 FAIL
DetailsDoug Chausow
Parcels need to be consolidated
Routing - PUBLIC WORKS4/10/2018 4/10/2018 PASS
DetailsRachael Beierle
Intake Approval  4/10/2018 FAIL
need to complete paperwork thru P & Z for a property lotline adjustment
Intake Approval  4/10/2018 PASS
Recd Pcfee & Taken To Pln CK  4/10/2018 DONE
erosion permit was paid for, for the intake fee
Plans ACCEPTED BY PLAN TECH  4/5/2018 DONE
Application received  3/26/2018 DONE
Application submitted via PDS Online on Mar 26 2018 11:18AM