FIRE-Final Inspection | 7/23/2019 | 7/24/2019 | 7/24/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Josh Phone #: ###-####
|
GRD-Other | 7/23/2019 | 7/24/2019 | 7/23/2019 | P | CANC |
Troy Cobbley
|
|
|
Josh Phone #: ###-####
|
GRD-Final | 7/19/2019 | 7/19/2019 | 7/19/2019 | A | DONE |
Tiffany Lowery
|
|
|
|
Issue PAID IN FULL permit | | | 7/5/2018 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 7/5/2018 | | DONE |
|
|
|
|
Routing - FRONT DESK | 6/14/2018 | | 6/21/2018 | | PASS |
Tiffany Carson-Herker
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/21/2018 | | DONE |
Christina Prado
|
|
|
NEED - All met
GC
RP
Rev cert of Val
Check to be mailed in, contact Jeff w/MJ Harris for issuance
###-#### or
|
Plan assigned to (TCH) TIffany | 5/29/2018 | | 6/21/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Routing - FIRE | 6/14/2018 | 6/14/2018 | 6/20/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - FRONT DESK | 5/29/2018 | | 6/4/2018 | | FAIL |
Tiffany Carson-Herker
|
|
|
Failed Due to Fire review
|
Routing - Design Review | 5/29/2018 | | 6/1/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - FIRE | 5/29/2018 | 5/29/2018 | 5/31/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLANNING | 5/29/2018 | | 5/30/2018 | | PASS |
Leon Letson
|
|
|
|
Routing PW Street Lights | 5/29/2018 | | 5/30/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 5/29/2018 | | 5/30/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 5/29/2018 | | 5/30/2018 | | PASS |
Evan Carpenter
|
|
|
No review required at this time for solid waste. Solid waste will be assessed on the BLD permit.
|
Routing PW Environmental | 5/29/2018 | | 5/30/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLUMBING | 5/29/2018 | | 5/29/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing PW Drainage | 5/29/2018 | | 5/29/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - Erosion and Sediment | 5/29/2018 | | 5/29/2018 | | PASS |
Michael Zawacki
|
|
|
Site prep inspection required. RP will need a valid con number or enrollment in RP class.
|
Routing - Addressing | 5/29/2018 | | 5/29/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/29/2018 | | 5/29/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/29/2018 | | DONE |
|
|
|
|
Intake Approval | | | 5/29/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/29/2018 | | DONE |
|
|
|
ESC plan check paid
|
Intake Approval | | | 5/25/2018 | | FAIL |
|
|
|
1. Please upload ONLY plans applicable to this application for a Grading and Drainage w/(underground) Utilities permit. See checklist link: https://pds.cityofboise.org/media/202126/524-commercial-grading-drainage-with-utilities-submittal-checklist_7-5-16.pdf
2. All plans must follow electronic submittal standards and be uploaded as separate files and named accordingly (example: C0 Civil Cover, C1.0 Grading and Drainage plan, etc..)
3. IF the Statement of Special Inspections form is applicable to structural shoring for grading plan please re-upload. There was an error on the file and it did not come through.
All plans (not documents) previously uploaded have been deleted for clarity.
|
Application received | | | 5/24/2018 | | DONE |
|
|
|
Application submitted via PDS Online on May 24 2018 4:01PM
|