CHANGE STATUS TO (ISS) | | | 12/11/2019 | | DONE |
|
|
|
Reopen permit per still working on phase 2, which is included in this grading permit. Phase 1 was for parcel R8207350150, and phase 2 is for parcel R8207350200 as indicated on approved plans.
|
FIRE-Final Inspection | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
Issue PAID IN FULL permit | | | 9/4/2018 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 9/4/2018 | | DONE |
|
|
|
|
Plan assigned to (CAN) Candy | 8/3/2018 | | 8/31/2018 | | DEFR |
Candy A. Nichols
|
|
|
|
Routing - PLAN CHECK | 8/3/2018 | | 8/31/2018 | | PASS |
Candy A. Nichols
|
|
|
|
Routing PW Sewer Design | 8/31/2018 | | 8/31/2018 | | PASS |
DeAnn Brown
|
|
|
|
Plan resubmittals received | | | 8/31/2018 | | DONE |
|
|
|
|
Plan assigned to Christina | 8/31/2018 | | 8/31/2018 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/31/2018 | | DONE |
|
|
|
MET
NEED
RP -met
GC FORM
REVSIED VALUE
|
Routing PW Drainage | 8/10/2018 | | 8/20/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 8/10/2018 | | 8/20/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - FIRE | 8/3/2018 | 8/3/2018 | 8/15/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Solid Waste | 8/10/2018 | | 8/13/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Environmental | 8/10/2018 | | 8/13/2018 | | PASS |
Terry Alber
|
|
|
No Pretreatment issues at this time.
|
Routing - PUBLIC WORKS | | | 8/10/2018 | | PASS |
|
|
|
|
Routing - PLANNING | 8/3/2018 | | 8/6/2018 | | PASS |
Katelyn Menuge
|
|
|
Grading okay - DRH18-00264
|
Routing - Addressing | 8/3/2018 | | 8/6/2018 | | PASS |
Doug Chausow
|
|
|
2 parcels need to be combined into 1. Spoke with Christine and they have a "cross access agreement", so I'll change this to PASS.
|
Routing - Erosion and Sediment | 8/3/2018 | | 8/6/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed prior to ground disturbing activities.
Site prep inspection required.
|
Application received | | | 8/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2018 9:40AM
|
Plans ACCEPTED BY PLAN TECH | | | 8/3/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/3/2018 | | PASS |
Candy A. Nichols
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/3/2018 | | DONE |
|
|
|
ESC permit fees paid for intake fees
|