Permit Information
Permit NumberGRD18-00065
StatusIssued
Name MCMILLEN LLC
Site Address 3206 W PLEASANTON AVE
Project NameBOISE WHITEWATER PARK PHASE 2
Customer Number 
ePlanReviewNo
Description
(BOISE WHITEWATER PARK - PHASE II) ****9/28/18 PLAN MODIFICATION TO ADD RIVER WORK INTO SCOPE OF WORK. WAS PREVIOUSLY REMOVED PENDING IDWR & IDAHO DEPT OF LANDS APPROVALS****Grading permit to excavate, grade and compact site earth materials in preparation for a phase II of the Esther Simplot Whitewater Park project. Project to consists of greenbelt trail relocations & restorations, pathways, site clearing activities including tree and debris stockpile removal, river diversion, ESC BMP installation and site lighting. Area disturbance is approx.18 acres, total site area. All work to be performed as approved by the Public Works Deptartment and Planning & Zoning Department, reference CFH17-00058 & CFH17-00061. THIS GRADING PERMIT DOES NOT INCLUDE BUILDINGS OR RIVER STRUCTURES. Seperate BLD permits required for proposed River structure, bridge pathways and maintenance building. (C_P)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GRD-Final8/20/20198/21/20198/21/2019ACANC
DetailsAndy J. Long
Please call before arrival so that I can meet at Esther Simplot Park (rear parking lot). Construction is complete so I will need 10 min lead time, if possible. Thank you! Phone #: ###-#### >> Inspection requested via web by Tyler Ross Inspection cancelled from web by: Tyler Ross
GRD-Final7/25/20197/26/20198/20/2019ACANC
Details
Phone #: ###-#### >> Inspection requested via web by Tyler Ross Inspection cancelled from web by: Tyler Ross
(F) Reprint permit  10/1/2018 DONE
CHANGE STATUS TO (ISS)  10/1/2018 DONE
Plan assigned to Christina  9/28/2018 DONE
DetailsChristina Prado
Routing - PLANNING  9/28/2018 PASS
DetailsLeon Letson
Routing PW Flood Plain9/26/2018 9/28/2018 PASS
DetailsJason C. Taylor
Inspection Record Card-GRD  9/28/2018 DONE
Telephone call  9/28/2018 DONE
Called Olivia to advise permit is ready to issue, no fees due
Permit Ready to Issue  9/28/2018 DONE
All requirements met; no fees due

DO NOT RE-ISSUE
Plan Modification Accepted  9/26/2018 DONE
Plan Mod came in-in river work that was not permited when GRD 1st was issued-received 2 each cover sheet, GOO1-G006, D001, D101-D106, GC001-GC004, C001-C004, C101-C103, C131-C138, C141, C201- and 2 Ada Cnty recordings TOOK TO C_P
Issue PAID IN FULL permit  9/12/2018 DONE
(F) Reprint permit  9/5/2018 DONE
DetailsRita DeYoung
Telephone call  8/31/2018 DONE
Spoke with Olivia and she said she will refill the 306 with grading values only
Routing PW Flood Plain8/30/2018 8/30/2018 PASS
DetailsJason C. Taylor
Plans redlined to remove all in river work. Once easements have been given then plans can be resubmited for approval. Jason Taylor ###-####
PLANS/APPL TAKEN TO FRONT DESK  8/30/2018 DONE
Inspection Record Card-GRD  8/30/2018 DONE
Permit Ready to Issue  8/30/2018 DONE
MET
Need:
Revised Certificate of Value (sent email to Olivia, 8/31/18, double checking grading value is 7+ million)

MET
GC Form
RP
Telephone call  8/30/2018 DONE
Called Olivia to inform her the permit is ready, we need a 302 and 306 form filled out.
Plan assigned to Christina8/6/2018 8/30/2018 DONE
DetailsChristina Prado
Routing - FRONT DESK  8/30/2018 PASS
DetailsChristina Prado
Routing - PLANNING8/30/2018 8/30/2018 PASS
DetailsLeon Letson
CFH17-00058, CFH17-00061 Need IDL, DEQ approval per Public Works Comments. Route back to Planning after Public Works signs off. LNL
Routing - PUBLIC WORKS  8/30/2018 PASS
DetailsRachael Beierle
Routing PW Flood Plain8/7/2018 8/27/2018 FAIL
DetailsJason C. Taylor
Need DEQ & IDL approval before issuance. Route back to PW FLoodplain. JCT
Routing - FIRE 8/6/20188/23/2018 CANC
DetailsErika Akin
No review required for IFC. Please coordinate with Boise Fire to ensure emergency response is not adversely impacted.
Routing - Erosion and Sediment  8/23/2018 PASS
DetailsAndy J. Long
ESC plan/SWPPP approved. Certified stormwater team designated. Pre-construction site preparation inspection is required. City inspection frequency at minimum of once every 2 weeks and during/after significant rain events.
Routing - Addressing8/6/2018 8/7/2018 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  8/6/2018 DONE
Intake Approval  8/6/2018 PASS
Recd Pcfee & Taken To Pln CK  8/6/2018 DONE
Application received 8/3/2018