(ACE CO PRECISION – Rough Grading) To conduct excavation of approximately 8000 cubic yards of earth in the site preparation for a new commercial building as approved by the City of Boise, Public Works Department. No structures, building construction, or site utility work is allowed under this permit. ESC18-01411 is to be issued with this permit. (BLH)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GRD-Final1/4/20191/4/20191/4/2019PPASS
DetailsJim Storey
Herb Phone #: ###-####
DOC - Permit Finaled1/4/20191/4/20191/4/2019PPASS
DetailsJim Storey
Herb Phone #: ###-####
Issue PAID IN FULL permit  10/31/2018 DONE
Inspection Record Card-GRD  10/31/2018 DONE
Routing PW Solid Waste10/30/2018 10/30/2018 PASS
DetailsEvan Carpenter
Routing - PLANNING10/30/2018 10/30/2018 PASS
DetailsKatelyn Menuge
Routing - FRONT DESK10/30/2018 10/30/2018 PASS
DetailsBrittany Hill
PLANS/APPL TAKEN TO FRONT DESK  10/30/2018 DONE
Permit Ready to Issue  10/30/2018 DONE
jwilson@k2cm.com
MET
NEED
GC
Rev cert of val
RP
Plan assigned to (BLH)Brittany10/9/2018 10/30/2018 DONE
DetailsBrittany Hill
Routing - PUBLIC WORKS10/9/2018 10/30/2018 PASS
DetailsMorgan Webb
Routing - FRONT DESK10/9/2018 10/22/2018 FAIL
DetailsBrittany Hill
FAIL due to Planning and PW Solid Waste Fail
Routing PW Environmental10/9/2018 10/11/2018 PASS
DetailsRick Christenson
Routing PW Drainage10/9/2018 10/11/2018 PASS
DetailsBrian Murphy
Routing - PLANNING10/9/2018 10/10/2018 FAIL
DetailsKatelyn Menuge
Please update drawing scales on Grading sheets.
Routing - Addressing10/9/2018 10/9/2018 PASS
DetailsDoug Chausow
Intake Approval  10/9/2018  
Recd Pcfee & Taken To Pln CK  10/9/2018 DONE
Routing PW Street Lights10/9/2018 10/9/2018 PASS
DetailsTom Marshall
Routing PW Sewer Design10/9/2018 10/9/2018 PASS
DetailsDeAnn Brown
No sewer work to be completed.
Routing PW Solid Waste10/9/2018 10/9/2018 FAIL
DetailsEvan Carpenter
The solid waste enclosure must have at least 18 feet of unobstructed clearance between gate posts (measured from the innermost points) for each pair of dumpsters.
Routing - Erosion and Sediment10/9/2018 10/9/2018 PASS
DetailsMichael Zawacki
RP needed prior to ground disturbing activities. Site prep inspection required.
Intake Approval  9/28/2018 FAIL
-Soils & Geotechnical report needs to be stamped and signed by an Idaho Licensed Engineer
-Erosion & Sediment Control Narrative needs to be signed by a plan designer certified by the City of Boise
Telephone call  9/28/2018 DONE
Spoke with Marcellus, should be a 526
Application received  9/26/2018 DONE
Application submitted via PDS Online on Sep 26 2018 6:19PM