GRD-Final | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | PASS |
Jim Storey
|
|
|
Herb Phone #: ###-####
|
DOC - Permit Finaled | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | PASS |
Jim Storey
|
|
|
Herb Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/31/2018 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 10/31/2018 | | DONE |
|
|
|
|
Routing PW Solid Waste | 10/30/2018 | | 10/30/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLANNING | 10/30/2018 | | 10/30/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - FRONT DESK | 10/30/2018 | | 10/30/2018 | | PASS |
Brittany Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/30/2018 | | DONE |
|
|
|
jwilson@k2cm.com
MET
NEED
GC
Rev cert of val
RP
|
Plan assigned to (BLH)Brittany | 10/9/2018 | | 10/30/2018 | | DONE |
Brittany Hill
|
|
|
|
Routing - PUBLIC WORKS | 10/9/2018 | | 10/30/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - FRONT DESK | 10/9/2018 | | 10/22/2018 | | FAIL |
Brittany Hill
|
|
|
FAIL due to Planning and PW Solid Waste Fail
|
Routing PW Environmental | 10/9/2018 | | 10/11/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Drainage | 10/9/2018 | | 10/11/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 10/9/2018 | | 10/10/2018 | | FAIL |
Katelyn Menuge
|
|
|
Please update drawing scales on Grading sheets.
|
Routing - Addressing | 10/9/2018 | | 10/9/2018 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 10/9/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/9/2018 | | DONE |
|
|
|
|
Routing PW Street Lights | 10/9/2018 | | 10/9/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 10/9/2018 | | 10/9/2018 | | PASS |
DeAnn Brown
|
|
|
No sewer work to be completed.
|
Routing PW Solid Waste | 10/9/2018 | | 10/9/2018 | | FAIL |
Evan Carpenter
|
|
|
The solid waste enclosure must have at least 18 feet of unobstructed clearance between gate posts (measured from the innermost points) for each pair of dumpsters.
|
Routing - Erosion and Sediment | 10/9/2018 | | 10/9/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed prior to ground disturbing activities. Site prep inspection required.
|
Intake Approval | | | 9/28/2018 | | FAIL |
|
|
|
-Soils & Geotechnical report needs to be stamped and signed by an Idaho Licensed Engineer
-Erosion & Sediment Control Narrative needs to be signed by a plan designer certified by the City of Boise
|
Telephone call | | | 9/28/2018 | | DONE |
|
|
|
Spoke with Marcellus, should be a 526
|
Application received | | | 9/26/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 26 2018 6:19PM
|