GRD-Final | 5/2/2019 | 5/3/2019 | 5/3/2019 | A | DONE |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
DOC - Permit Finaled | 5/3/2019 | 5/3/2019 | 5/3/2019 | A | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
GRD-Final | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PEND |
Dave Hannah
|
|
|
Mike Phone #: ###-#### needs pw first
|
Zoning Approval | 4/29/2019 | 4/29/2019 | 4/29/2019 | | PASS |
Josh Wilson
|
|
|
|
Inspection Record Card-GRD | | | 1/29/2019 | | DONE |
|
|
|
|
Routing PW Sewer Design | 1/25/2019 | | 1/28/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - FRONT DESK | 1/28/2019 | | 1/28/2019 | | PASS |
Brittany Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/28/2019 | | DONE |
|
|
|
All met
NEED
rp
met
GC
Rev cert of val
Email permit to Michele Rodgers
|
Issue PAID IN FULL permit | | | 1/28/2019 | | DONE |
|
|
|
|
Routing - FIRE | | 12/26/2018 | 1/25/2019 | | PASS |
Erika Akin
|
|
|
No structures involved. No impact to FD access. No comments attached.
|
Routing PW Drainage | 12/24/2018 | | 1/25/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 12/24/2018 | | 1/2/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Solid Waste | 12/24/2018 | | 1/2/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Sewer Design | 12/24/2018 | | 12/26/2018 | | FAIL |
DeAnn Brown
|
|
|
Add sewer plug permit language to note 7 on sheet C1.01.
|
Routing - Design Review | 12/26/2018 | | 12/26/2018 | | PASS |
Josh Wilson
|
|
|
OK per DRH18-00422
|
Routing - Erosion and Sediment | 12/24/2018 | | 12/24/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan is approved. RP listed is not yet certified. Provide certified RP prior to permit issue. Site preparation inspection is REQUIRED.
|
Intake Approval | | | 12/19/2018 | | FAIL |
|
|
|
The storm water management & Engineering Drainage Report has a stamp, but still no signature
|
Intake Approval | | | 12/13/2018 | | FAIL |
|
|
|
1st prescreen 12-13-18 : (DEMO permit will need to be applied & issued for before this grading permit can be issued)
Please finish filling out check list & sign,
please provide Specification book,
Soils & Geotechnical Report,
site specific fire flow at hydrants letter from suez water,
site drainage report stamped and singed by Idaho licensed designer,
Drainage System operation & maintenance plan stamped and signed by Idaho licensed designer & the Appendix J
plan sheet showing location of designating fire hydrants
|
Intake Approval | | | 12/13/2018 | | FAIL |
|
|
|
2nd Prescreen 12-13-18: Demo permit can not be applied for through this permit, needs to be done separately (I have deleted that file from your documents).
Appendix J is required,
The storm water management & Engineering Drainage Report is not signed by the engineer,
a new letter from suez (more current date: old one has 2016 for the year) is needed.
As for the fire hydrant plan(s) you are welcome to put the location on your site plan we just have to know where they are located.
|
Application received | | | 12/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 7 2018 2:29PM
|
Telephone call | | | 12/7/2018 | | DONE |
|
|
|
spoke with Roger informing him that the demo permit will need to be applied for as well
|