FIRE-Final Inspection | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. One new fire hydrant located near entrance on Cole Road. The new underground supply lines for the new sprinkler systems installed under separate permits.
called ahead - screened // Cody Phone #: ###-####
|
GRD-Public Works Approval | 4/20/2020 | 4/20/2020 | 4/20/2020 | | DONE |
Tiffany Lowery
|
|
|
|
Telephone call | | | 4/20/2020 | | DONE |
|
|
|
Spoke with Cody from Datum Construction. Scheduled fire life safety, but they've already passed BLD final. Will have to check back after monday at 5 to see if he passed, then check with Tell to make sure that BLD can be finaled.
|
GRD-Final | 4/16/2020 | 4/17/2020 | 4/17/2020 | P | DONE |
Tell Riley
|
|
|
Screened- Cody Phone #: ###-####//per discussion with Jason Taylor, no structural inspecitons were needed for GRD permit//permit details show structural sign off was required//
|
GRD-Final | 4/15/2020 | 4/15/2020 | 4/15/2020 | P | CANC |
Tell Riley
|
|
|
Cody Phone #: ###-####//email sent to Jason Taylor regarding this permit//let contact know//
|
Inspection Record Card-GRD | | | 12/26/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/6/2019 | | DONE |
|
|
|
|
Telephone call | | | 9/5/2019 | | DONE |
|
|
|
emailed keith@datumconstruction.com and gwalker@adpboise.com to let them know that I cannot issue this permit until we have an up to date RP. The RP listed has expired.
|
Plan Reviewer's activity | | | 5/6/2019 | | DONE |
|
|
|
05.06.2019. Grading plans showed fire sprinkler lines for buildings. Building permit BLD 19-00323 and BLD 19-00326 require fire sprinklers for building permit. Case noted in tidemark by MS.
|
Plan assigned to (GF) Gemma | 4/10/2019 | 4/10/2019 | 5/3/2019 | | DONE |
Gemma Flores
|
|
|
|
Routing - FRONT DESK | 4/10/2019 | | 5/3/2019 | | PASS |
Gemma Flores
|
|
|
|
1st review completed | | | 5/3/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/3/2019 | | DONE |
|
|
|
email keith@datumconstruction.com
MET
NEED
RP
GC FORM
REVISED VALUE
|
Inspection Record Card-GRD | | | 5/3/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/3/2019 | | DONE |
|
|
|
Spoke with Glenn to inform hi the permit is ready and that we need the GC form and certificate of value from the GC.
|
Routing - FIRE | 5/1/2019 | 5/1/2019 | 5/2/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Review complete. Uploaded report. passed.
|
Plan resubmittals received | | | 5/1/2019 | | DONE |
Gemma Flores
|
|
|
Resubmittal from Seijoon Son. Pages C1 - C5
|
Routing - PLUMBING | 4/24/2019 | | 5/1/2019 | | PASS |
Dan Ediger
|
|
|
No plumbing involved.
|
Meeting | | | 4/30/2019 | | DONE |
|
|
|
Mark spoke with me about resubmittal without activity. Emailed Sijoon Song, letting him know that we need a second paper set.
|
Routing - FIRE | 4/10/2019 | 4/10/2019 | 4/26/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC review complete. Plans missing Fire Service Lines. Uploaded IFC 1st Review 04.26.2019.pdf
|
Routing - Erosion and Sediment | 4/10/2019 | | 4/24/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified Plan Desinger listed, need to provide a certified ESC Responsible Person with operational control at the site. Site preparation inspection REQUIRED.
|
Routing - PLANNING | 4/19/2019 | | 4/19/2019 | | PASS |
Katelyn Menuge
|
|
|
Redlined Changes
|
Routing PW Drainage | 4/18/2019 | | 4/18/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 4/10/2019 | | 4/18/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Solid Waste | 4/16/2019 | | 4/17/2019 | | PASS |
Evan Carpenter
|
|
|
No changes to solid waste.
|
Routing PW Drainage | 4/12/2019 | | 4/16/2019 | | FAIL |
Brian Murphy
|
|
|
NEED APDX J FILL OUT
|
Routing PW Street Lights | 4/16/2019 | | 4/16/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - Addressing | 4/10/2019 | | 4/12/2019 | | PASS |
Doug Chausow
|
|
|
3 parcels must be consolidated prior to any building.
|
Plans ACCEPTED BY PLAN TECH | | | 4/10/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/10/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/10/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/3/2019 | | FAIL |
|
|
|
Need Appendix J, site drainage, application and finish filling out checklist
|
GRD-Other | 9/11/2019 | 9/16/2019 | | P | |
|
|
|
vertical curve around island // Joston Phone #: ###-####
|
Application received | | 4/3/2019 | | | |
|
|
|
|