GRD-Public Works Approval | 5/11/2020 | 5/11/2020 | 5/11/2020 | | DONE |
Tiffany Lowery
|
|
|
|
GRD-Final | 2/4/2020 | 2/4/2020 | 2/4/2020 | P | PASS |
Troy Cobbley
|
|
|
Per Jim, life safety ok to pass. Phone #: 2084073234 >> Inspection requested via mobile web by Allen Nunnally
|
Permit Ready to Issue | | | 6/25/2019 | | DONE |
|
|
|
ALL MET- Need GC
Need Rev Val
|
Issue PAID IN FULL permit | | | 6/25/2019 | | DONE |
|
|
|
|
Inspection Record Card-GRD | | | 6/25/2019 | | DONE |
|
|
|
|
Routing PW Street Lights | 6/21/2019 | | 6/24/2019 | | PASS |
Tom Marshall
|
|
|
|
1st review completed | | | 6/24/2019 | | DONE |
|
|
|
|
Routing - FRONT DESK | 6/24/2019 | | 6/24/2019 | | PASS |
Tiffany Carson-Herker
|
|
|
|
Routing - PLANNING | 6/24/2019 | | 6/24/2019 | | PASS |
Josh Wilson
|
|
|
per design review routing
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/2019 | | DONE |
|
|
|
|
Routing PW Drainage | 6/21/2019 | | 6/21/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 6/21/2019 | | 6/21/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - FRONT DESK | 6/21/2019 | | 6/21/2019 | | FAIL |
Tiffany Carson-Herker
|
|
|
Fail due to Street lights
|
Routing - FRONT DESK | 6/19/2019 | | 6/19/2019 | | FAIL |
Tiffany Carson-Herker
|
|
|
Fail due to PW Drainage and PW Street Lights
|
Routing PW Street Lights | 6/17/2019 | | 6/19/2019 | | FAIL |
Tom Marshall
|
|
|
Read the comments.
|
Routing - Design Review | 6/17/2019 | | 6/18/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing - FRONT DESK | 5/30/2019 | | 6/10/2019 | | FAIL |
Tiffany Carson-Herker
|
|
|
Fail due to Planning, PW Drainage and PW Street Lights.
|
Routing PW Solid Waste | 5/31/2019 | | 6/10/2019 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Flood Plain | 5/31/2019 | | 6/10/2019 | | CANC |
Jason C. Taylor
|
|
|
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - FIRE | 5/30/2019 | 5/30/2019 | 6/7/2019 | | PASS |
Mark Scharfen
|
|
|
06.07.2019-Completed fire review. FD access, hydrant, fire flow meets code. Approved.
|
Routing - PUBLIC WORKS | 5/30/2019 | | 5/31/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Street Lights | 5/31/2019 | | 5/31/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 5/31/2019 | | 5/31/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PLANNING | 5/30/2019 | | 5/31/2019 | | FAIL |
Andrea Tuning
|
|
|
To comply with DRH19-00111: 1. Increase trash enclosure depth to 12 feet per Solid Waste comments 2. Provide recorded agreement allowing landscaping within recorded Access Easement
|
Routing - Addressing | 5/30/2019 | | 5/30/2019 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/30/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/30/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/30/2019 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 5/30/2019 | | 5/30/2019 | | PASS |
Michael Zawacki
|
|
|
Site prep required.
|
Routing - PLUMBING | 5/30/2019 | | 5/30/2019 | | PASS |
Daryl Spivey
|
|
|
Grading only
|
Intake Approval | | | 5/29/2019 | | FAIL |
|
|
|
Please provide a copy of the Erosion & Sediment Control Narrative in the documents folder.
|
Intake Approval | | | 5/28/2019 | | FAIL |
|
|
|
I have deleted all drawings in this grading permit. Please only upload the drawings that are for the grading with utilities only. No buildings or footings are allowed to be constructed under this permit.
|
Application received | | | 5/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 24 2019 3:55PM
|
Plan assigned to (TCH) TIffany | 5/30/2019 | | | | |
Tiffany Carson-Herker
|
|
|
|
Routing PW Drainage | 5/31/2019 | | | | FAIL |
Brian Murphy
|
|
|
NEED PERCTEST OVER 0.5'/HR
|
Routing PW Drainage | 6/17/2019 | | | | FAIL |
Brian Murphy
|
|
|
NEED BTTOM OF SEEPAGE BED NOTE FOR DETAIL
|