Plan assigned to (BLH)Brittany | 2/20/2020 | | 2/26/2020 | | DONE |
Brittany Hill
|
|
|
|
Routing - FRONT DESK | 2/20/2020 | | 2/26/2020 | | PASS |
Brittany Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/26/2020 | | DONE |
|
|
|
plan mod approved
|
Routing PW Sewer Design | 2/20/2020 | | 2/25/2020 | | PASS |
DeAnn Brown
|
|
|
PLAN MOD
|
Routing PW Drainage | 2/20/2020 | | 2/25/2020 | | PASS |
Brian Murphy
|
|
|
PLAN MOD
|
Routing PW Solid Waste | 2/20/2020 | | 2/24/2020 | | PASS |
Evan Carpenter
|
|
|
PLAN MOD
|
Routing PW Environmental | 2/20/2020 | | 2/21/2020 | | PASS |
Rick Christenson
|
|
|
PLAN MOD
|
Routing - PUBLIC WORKS | 2/20/2020 | | 2/20/2020 | | PASS |
Candy A. Nichols
|
|
|
PLAN MOD
|
Routing - Erosion and Sediment | 2/20/2020 | | 2/20/2020 | | PASS |
Michael Zawacki
|
|
|
|
Plan Modification Accepted | | | 2/20/2020 | | DONE |
|
|
|
Basalt rock was encountered at the seepage bed location and additional soils and percolation testing was completed to revise the seepage bed design to accommodate the rock layer also changing the seepage bed section (the layered subgrade materials of the bed). Bed length and width was maintained.
|
GRD-Grading Inspection | 11/13/2019 | 11/14/2019 | 11/14/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Rod Baxter
|
GRD-Grading Inspection | 10/18/2019 | 10/18/2019 | 10/18/2019 | A | CANC |
|
|
|
Please call Rod at given PH # when en- route Phone #: ###-#### >> Inspection requested via web by Philip Allen Inspection cancelled from web by: Rod Baxter
|
Telephone call | | | 10/4/2019 | | DONE |
|
|
|
Joshua sent me a revied revised cert of val-i deleted the old value and fees-redid them and emailed him the new fees
|
Issue PAID IN FULL permit | | | 10/4/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/24/2019 | | DONE |
|
|
|
all met: joshuajackson@esiconstruction.com
Need
RP
GC Form
Revised Value
|
Plan assigned to (CAN) Candy | 8/23/2019 | | 9/24/2019 | | DONE |
Candy A. Nichols
|
|
|
|
Routing - FRONT DESK | 8/23/2019 | | 9/24/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - FIRE | 9/12/2019 | 9/12/2019 | 9/23/2019 | | PASS |
Mark Scharfen
|
|
|
Attached comments to case
|
Routing PW Sewer Design | 9/12/2019 | | 9/20/2019 | | PASS |
DeAnn Brown
|
|
|
New sewer extension plans created and uploaded. Sewer extension design is approved. Inspection fees will be due prior to construction.
|
Routing PW Drainage | 9/12/2019 | | 9/18/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 9/13/2019 | | 9/13/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - FIRE | 8/23/2019 | 8/23/2019 | 9/5/2019 | | FAIL |
Mark Scharfen
|
|
|
09/05-9605 S. Eisenman Grading fire review complete. Uploaded and emailed applicant rev_fire 09.05.2019.pdf
|
Routing PW Drainage | 8/23/2019 | | 9/3/2019 | | FAIL |
|
|
|
need apdx j,overflow for pond, air pump
|
Routing - Erosion and Sediment | 8/23/2019 | | 8/27/2019 | | PASS |
Michael Zawacki
|
|
|
RP needed, site prep inspection required.
SWPPP submitted is prebid and does not list contractors or RP
|
Routing PW Environmental | 8/23/2019 | | 8/27/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 8/23/2019 | | 8/26/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Street Lights | 8/23/2019 | | 8/26/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 8/23/2019 | | 8/23/2019 | | FAIL |
DeAnn Brown
|
|
|
Sewer extension plans have not been reviewed and approved by City of Boise Public Works. Please submit pdf of sewer extension plans for review to DeAnn Brown.
|
Routing PW Grading-Hillside | 8/23/2019 | | 8/23/2019 | | CANC |
Melissa Jannusch
|
|
|
No hillside review needed
|
Routing - Addressing | 8/23/2019 | | 8/23/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/23/2019 | | 8/23/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 8/23/2019 | | 8/23/2019 | | FAIL |
Katelyn Menuge
|
|
|
Need updated plans reflecting ACHD requirements.
|
Intake Approval | | | 8/23/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/23/2019 | | DONE |
|
|
|
ESC fees paid for intake
|
Intake Approval | | | 8/19/2019 | | FAIL |
|
|
|
per applicant Jason-needs all drawings deleted-has name changes to make
|
Application received | | | 8/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 16 2019 4:06PM
|
GRD-Other | 10/18/2019 | 10/21/2019 | | A | |
|
|
|
Erosion Control Inspection..Please Call when en route. Phone #: ###-#### >> Inspection requested via web by Rod Baxter
|
GRD-Grading Inspection | 10/18/2019 | 10/18/2019 | | P | |
|
|
|
Please Call when headed to site, would like to meet you onsite Phone #: ###-#### >> Inspection requested via web by Rod Baxter
|