Final | 2/20/2001 | 2/20/2001 | 2/20/2001 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 02/20/2001 at 08:15:32. Contact: ###-####.
|
Rough-in | 10/31/2000 | 11/1/2000 | 11/1/2000 | A | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 10/31/2000 at 14:41:47. Contact: ###-####.
|
Pressure Test | 10/31/2000 | 11/1/2000 | 11/1/2000 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 10/31/2000 at 14:42:07. Contact: ###-####.
|
Rough-in | 11/1/2000 | 11/1/2000 | 11/1/2000 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/01/2000 at 10:52:23. Contact: ###-####.
|
Rough-in | 11/1/2000 | 11/1/2000 | 11/1/2000 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 11/01/2000 at 10:52:23. Contact: ###-####.
|
Application received | | | 8/1/2000 | | |
|
|
|
|
Issue & PRINT permit | | | | | |
|
|
|
|