Final | 12/26/2000 | 12/27/2000 | 12/27/2000 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/26/2000 at 08:43:33. Contact: ###-####.
|
Pressure Test | 11/21/2000 | 11/22/2000 | 11/22/2000 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/21/2000 at 14:36:38. Contact: ###-####.
|
Pressure Test | 11/20/2000 | 11/21/2000 | 11/21/2000 | A | NR |
Dixie Fellows
|
|
|
Amy ###-####... 11/21/2000 12:00:06 PM...not even close 11/21/2000 12:00:51 PM
|
Pressure Test | 11/21/2000 | 11/21/2000 | 11/21/2000 | P | FAIL |
Dixie Fellows
|
|
|
Added by Inspector: 411 On 11/21/2000 12:18:08 PM gas pipe undersized
|
Rough-in | 11/17/2000 | 11/20/2000 | 11/20/2000 | A | PASS |
Jim Sly
|
|
|
amy ###-####
|
Rough-in | 11/13/2000 | 11/15/2000 | 11/15/2000 | A | NR |
Tom Arcoraci
|
|
|
###-####
|
Application received | | | 10/18/2000 | | |
|
|
|
|
Issue & PRINT permit | | | 10/18/2000 | | DONE |
|
|
|
|