Third Notice MEC | 6/12/2003 | 6/12/2003 | 4/1/2004 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notification | 5/8/2003 | 5/8/2003 | 6/12/2003 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 5/23/2002 | 5/8/2003 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/23/2002 | | DONE |
|
|
|
|
Final | 5/16/2002 | 5/16/2002 | 5/16/2002 | P | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 05/16/2002 at 10:37:24. Contact: ###-####.
|
DOC - Permit Finaled | 5/16/2002 | 5/16/2002 | 5/16/2002 | P | PASS |
Alan Hauser
|
|
|
Finaled by inspector at 5/16/2002 3:38:46 PM
|
Final | 5/7/2002 | 5/8/2002 | 5/8/2002 | A | CANC |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 05/07/2002 at 15:46:49. Contact: ###-####. unable to make contact with cont 5/9/2002 4:11:42 PM
|
Final | 5/1/2002 | 5/2/2002 | 5/2/2002 | A | PART |
Alan Hauser
|
|
|
finish one s.a. run at entrance and finish condensate drains at rtu s 5/2/2002 10:11:14 AM
|
Final | 4/30/2002 | 4/30/2002 | 4/30/2002 | P | NR |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 04/30/2002 at 07:55:54. Contact: ###-####.
|
Pressure Test | 4/11/2002 | 4/11/2002 | 4/11/2002 | P | PASS |
Dixie Fellows
|
|
|
###-#### ben...60# test ok 4/11/2002 2:13:48 PM
|
Pressure Test | 4/10/2002 | 4/10/2002 | 4/10/2002 | P | FAIL |
Dixie Fellows
|
|
|
###-#### guage pegged 4/10/2002 2:16:58 PM
|
Rough-in | 3/27/2002 | 3/28/2002 | 3/28/2002 | A | PART |
Alan Hauser
|
|
|
duct only , ok, no ceiling or diff. hook up 3/28/2002 9:53:47 AM
|
Application received | | | 2/1/2002 | | |
|
|
|
|
Issue & PRINT permit | | | 2/1/2002 | | DONE |
|
|
|
|