Final | 4/14/2003 | 4/15/2003 | 4/15/2003 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 4/14/2003 at 4:27:40 PM. Contact: ###-####.
|
DOC - Permit Finaled | 4/15/2003 | 4/15/2003 | 4/15/2003 | P | PASS |
Dixie Fellows
|
|
|
Finaled by inspector at 4/15/2003 3:19:58 PM
|
Pressure Test | 12/24/2002 | 12/26/2002 | 12/26/2002 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/24/2002 at 15:21:36. Contact: ###-####.
|
Rough-in | 12/18/2002 | 12/18/2002 | 12/18/2002 | A | FAIL |
Alan Hauser
|
|
|
Dixie / Tony,
Sent seperate e-mail to Tony explaining what I had done to correct yesterday's deficiencies. I went ahead and did this instead of Glynn's because I wanted to try and maintain my drywall schedule. Hope this is alright. I am out of town today so will not be able to be there for the inspection.; Phone #: ###-#### Internet Inspection Request from: Richard Fritzley
|
Final | 12/18/2002 | 12/18/2002 | 12/18/2002 | P | NR |
Alan Hauser
|
|
|
###-####--JEFF
|
Rough-in | 12/18/2002 | 12/18/2002 | 12/18/2002 | P | PART |
Alan Hauser
|
|
|
oval pipe at basement has 61.2612 square inches of area. contractor didn't know total btu load at equipment room. will have to check at final, if not enough combustion air, then will have to add more. 12/18/2002 7:34:17 PM
|
Rough-in | 12/17/2002 | 12/17/2002 | 12/17/2002 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/17/2002 at 09:34:46. Contact: ###-####.c/n posted 12/17/2002 10:27:53 PM
|
Rough-in | 12/12/2002 | 12/12/2002 | 12/12/2002 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/12/2002 at 08:33:09. Contact: ###-####. called cont to schedule a conference 12/12/2002 3:09:25 PM
|
Pressure Test | 12/12/2002 | 12/12/2002 | 12/12/2002 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/12/2002 at 08:33:44. Contact: ###-####.
|
Rough-in | 12/4/2002 | 12/5/2002 | 12/5/2002 | A | FAIL |
Dixie Fellows
|
|
|
rescheduled...ran out of time doors all locked 12/5/2002 9:48:36 AM
|
Rough-in | 12/3/2002 | 12/4/2002 | 12/4/2002 | A | NR |
Carl Dependahl
|
|
|
###-#### includes fireplaces...need gas demand diagram, recall. 12/4/2002 10:35:04 AM
|
Rough-in | 12/4/2002 | 12/4/2002 | 12/4/2002 | P | CANC |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 12/04/2002 at 11:22:03. Contact: ###-####. out of time..will reschedule 12/4/2002 6:51:44 PM
|
Application received | | | 12/3/2002 | | |
|
|
|
|
Issue permit | | | 12/3/2002 | | DONE |
|
|
|
|