Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberMEC03-00707
StatusFinaled
Name HOBSON FABRICATION CORPORATION
Site Address 190 E FRONT ST
Project Name(CIVIC PLAZA PA3-APARTMENTS
Customer NumberR8354
ePlanReview 
Description
INSTALLING NEW HVAC...PER INITIAL CERT OF VALUE $ 430,000.00 ( CIVIC PLAZA -2 )
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice MEC5/6/20045/6/20046/23/2005 DONE
Second Notice has not been responded to.
First Notice Sent 4/2/20044/21/2004 DONE
DOC - Permit Finaled4/2/20044/2/20044/2/2004PPASS
DetailsAlan Hauser
Finaled by inspector at 4/2/2004 2:24:09 PM
Final4/1/20044/2/20044/2/2004AFAIL
DetailsTroy James
Phone #: ###-#### Internet Inspection Request from: RaChelle Meister
Provide the required combustion air at boilers within 12" of floor. Provide calcs showing how much air is being exhausted by the dryers to factor in the required duct size for make-up air. 4/2/2004 11:16:56 AM
Final4/2/20044/2/20044/2/2004PPASS
DetailsAlan Hauser
Phone #: ###-#### Internet Inspection Request from: RaChelle Meister
Final3/11/20043/12/20043/12/2004AFAIL
DetailsDixie Fellows
Phone #: ###-#### Internet Inspection Request from: RaChelle Meister
Final2/19/20042/20/20042/20/2004APART
DetailsAlan Hauser
all rooms ok, only thing left is combustion air into boiler room on roof 2/20/2004 12:15:42 PM
Final2/17/20042/18/20042/18/2004APART
DetailsAlan Hauser
all rooms on 6th floor ok 2/18/2004 11:20:07 AM
Final2/12/20042/13/20042/13/2004APART
DetailsAlan Hauser
all rooms ok on 5th floor 2/13/2004 12:36:44 PM
Final2/11/20042/12/20042/12/2004APART
DetailsAlan Hauser
4th floor rooms ok 2/12/2004 12:39:42 PM
Final2/10/20042/11/20042/11/2004APART
DetailsAlan Hauser
Phone #: ###-#### Internet Inspection Request from: RaChelle Meister
Final2/11/20042/11/20042/11/2004PPART
DetailsAlan Hauser
3rd floor rooms ok 2/11/2004 2:53:07 PM
Final1/29/20041/30/20041/30/2004APART
DetailsAlan Hauser
2nd flr. final except hallways 1/30/2004 1:09:18 PM
Rough-in1/22/20041/22/20041/22/2004APART
DetailsAlan Hauser
talked to rich about grease duct penetration through first floor ceiling into court yard shaft, ok to offset over to get 6" clearance in shaft 1/22/2004 10:33:53 AM
Rough-in1/20/20041/21/20041/21/2004APART
DetailsAlan Hauser
Rich; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
Rough-in1/21/20041/21/20041/21/2004PPART
DetailsAlan Hauser
Rough-in1/20/20041/20/20041/20/2004PFAIL
DetailsAlan Hauser
no answer to my three phone calls, recall when rich is back 1/20/2004 5:19:54 PM
Override - Parcel Holds1/1/19001/1/19001/20/2004  
Rough-in1/5/20041/6/20041/6/2004APASS
DetailsAlan Hauser
final on garage area only 1/6/2004 10:44:37 AM
Override - Parcel Holds  1/5/2004  
Rough-in12/29/200312/30/200312/30/2003ACANC
DetailsDixie Fellows
###-#### Rich TALKED TO RICH AND HE WILL RESCHEDULE WITH ALAN FOR FRI AM 12/30/2003 10:44:46 AM
Override - Parcel Holds  12/29/2003  
Rough-in12/17/200312/17/200312/17/2003PPART
DetailsAlan Hauser
unit on flrst floor elevator lobby 12/17/2003 3:11:57 PM
Override - Parcel Holds  12/17/2003  
Rough-in12/2/200312/3/200312/3/2003APART
DetailsAlan Hauser
rich-- ###-####
Override - Parcel Holds  12/2/2003  
Rough-in11/13/200311/13/200311/13/2003APART
DetailsAlan Hauser
dryers done on 4th floor 11/13/2003 1:42:34 PM
Rough-in11/4/200311/5/200311/5/2003APASS
DetailsAlan Hauser
last units for r/i 11/5/2003 2:51:05 PM
Rough-in10/23/200310/24/200310/24/2003APART
DetailsAlan Hauser
5th floor ok 10/24/2003 5:27:42 PM
Rough-in10/24/200310/24/200310/24/2003PPART
DetailsAlan Hauser
Rough-in10/22/200310/23/200310/23/2003ACANC
DetailsDave Lightfoot
Phone #: ###-#### Internet Inspection Request from: RaChelle Meister
Rough-in10/20/200310/21/200310/21/2003APART
DetailsAlan Hauser
looked at more dryer vents on 3, two left to complete 10/21/2003 1:57:58 PM
Rough-in10/14/200310/15/200310/15/2003APART
DetailsAlan Hauser
looked at wall r/i on 4th floor 10/15/2003 2:28:20 PM
Rough-in10/6/200310/7/200310/7/2003APART
DetailsAlan Hauser
looked at dryer vents in furred down areas on 2nd 10/7/2003 1:27:41 PM
Rough-in10/1/200310/2/200310/2/2003APART
DetailsAlan Hauser
Rough-in10/1/200310/1/200310/1/2003PPART
DetailsAlan Hauser
all of 3rd flr. except two, wall and exhaust only 10/2/2003 4:29:35 PM
Rough-in9/23/20039/24/20039/24/2003APART
DetailsDave Lightfoot
Phone #: ###-#### Internet Inspection Request from: RaChelle Meister 3rd floor exhaust shafts ok 9/24/2003 10:45:04 AM
Rough-in9/22/20039/23/20039/23/2003PCANC
DetailsDave Lightfoot
3RD FLOOR EAST. THANKS!!; Phone #: ###-#### Internet Inspection Request from: RaChelle Meister
Rough-in9/15/20039/16/20039/16/2003APART
DetailsAlan Hauser
west 1st flr ok 9/16/2003 11:06:04 AM
Rough-in9/9/20039/10/20039/10/2003APART
DetailsAlan Hauser
Phone #: ###-#### Internet Inspection Request from: RaChelle Meister partial inspection on 2nd flr. east units, dryer vents in wall only, bath exhaust don e 9/10/2003 10:09:31 AM
MEC-Aging Inspection8/25/20038/25/20038/25/2003 CANC
DetailsAlan Hauser
MEC-Aging Inspection6/25/20036/25/20036/25/2003 NR
DetailsAlan Hauser
Application received  3/21/2003  
Issue & PRINT permit  3/21/2003 DONE