Final | 3/25/2005 | 3/25/2005 | 3/25/2005 | P | DONE |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/25/2005 at 2:52:43 AM. Contact: ###-####. 350 3/25/2005 3:36:47 PM
|
Final | 3/25/2005 | 3/25/2005 | 3/25/2005 | P | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 3/25/2005 at 2:52:43 AM. Contact: ###-####.
|
DOC - Permit Finaled | 3/25/2005 | 3/25/2005 | 3/25/2005 | P | PASS |
Alan Hauser
|
|
|
Finaled by inspector at 3/25/2005 2:37:09 PM
|
Rough-in | 2/3/2005 | 2/3/2005 | 2/3/2005 | A | CANC |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 2/3/2005 at 4:14:10 AM. Contact: ###-####.
|
Rough-in | 2/3/2005 | 2/3/2005 | 2/3/2005 | P | PASS |
Lane Manuel
|
|
|
meeting am
|
Application received | | | 2/2/2005 | | |
|
|
|
|
Issue permit | | | 2/2/2005 | | DONE |
|
|
|
|