Final | 7/11/2005 | 7/11/2005 | 7/11/2005 | P | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 7/11/2005 at 9:13:51 AM. Contact: ###-####.
|
Rough-in | 6/7/2005 | 6/8/2005 | 6/8/2005 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 6/7/2005 at 1:39:21 PM. Contact: ###-####.
|
Rough-in | 6/6/2005 | 6/7/2005 | 6/7/2005 | A | FAIL |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 6/6/2005 at 12:46:22 PM. Contact: ###-####.
|
Pressure Test | 6/6/2005 | 6/7/2005 | 6/7/2005 | A | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 6/6/2005 at 12:46:35 PM. Contact: ###-####.
|
Application received | | | 6/2/2005 | | |
|
|
|
|
Issue permit | | | 6/2/2005 | | DONE |
|
|
|
|