Final | 6/15/2005 | 6/15/2005 | 6/15/2005 | | PASS |
Dixie Fellows
|
|
|
per dixie fn
|
CHANGE STATUS TO (FNL) | | | 6/15/2005 | | DONE |
|
|
|
per dixie permit is fn
|
Final | 6/10/2005 | 6/10/2005 | 6/10/2005 | A | PART |
Dixie Fellows
|
|
|
per dixie ...temp occ issued..model # on make-up air doesn't match engineered plans
|
Final | 6/8/2005 | 6/9/2005 | 6/9/2005 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 6/8/2005 at 2:17:24 PM. Contact: ###-####....need revised plans indicating equipment change to match air balance calcs..install restraining devise on equipment under the hood
|
Final | 6/3/2005 | 6/6/2005 | 6/6/2005 | A | FAIL |
Dixie Fellows
|
|
|
bob campbell ###-####...need air balance along with engineers calcs...need detectors in make-up air..re-route condensate over window...need make-up air for furnace above grid
|
Issue permit | | | 6/3/2005 | | DONE |
|
|
|
|
Application received | | | 6/3/2005 | | |
|
|
|
|