Third Notice MEC | 3/23/2007 | 3/23/2007 | 4/5/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice MEC | 3/2/2007 | 3/2/2007 | 3/23/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 1/29/2007 | 1/29/2007 | 3/2/2007 | | DONE |
Troy James
|
|
|
|
Final | 1/22/2007 | 1/29/2007 | 1/29/2007 | A | PASS |
Troy James
|
|
|
|
MEC-Aging Inspection | 1/16/2007 | 1/16/2007 | 1/17/2007 | | PASS |
Dixie Fellows
|
|
|
wip
|
MEC-Aging Inspection | 11/13/2006 | 11/13/2006 | 11/13/2006 | | PASS |
Dixie Fellows
|
|
|
HOTEL JOB...WORK IN PROGRESS
|
MEC-Aging Inspection | 9/11/2006 | 9/11/2006 | 9/11/2006 | | PASS |
Dixie Fellows
|
|
|
HOTEL...WIP
|
Rough-in | 7/12/2006 | 7/12/2006 | 7/12/2006 | P | PASS |
Troy James
|
|
|
fsd at 5th floor and shaft at vending from sixth to 11the floor, still need shaft built around duct that terminates exterior
|
Rough-in | 7/11/2006 | 7/11/2006 | 7/11/2006 | P | PASS |
Troy James
|
|
|
did walk through to verify progress in building for lee rice
|
Rough-in | 6/21/2006 | 6/21/2006 | 6/21/2006 | A | PART |
Troy James
|
|
|
ok fsd at 5th floor and 10th floor vending, duct exiting shaft at vending south end required to have fsd
|
Rough-in | 6/15/2006 | 6/15/2006 | 6/15/2006 | A | PASS |
Troy James
|
|
|
ok to cover ceilings at bathrooms on 10th floor
|
Rough-in | 5/17/2006 | 5/17/2006 | 5/17/2006 | P | PASS |
Troy James
|
|
|
ok fsd at shafts up to 10th floor except at vending areas not completed
|
Final | 4/12/2006 | 4/17/2006 | 4/17/2006 | A | CANC |
Troy James
|
|
|
meet mike wisdom at 10:30 met last friday
|
Conference | 4/13/2006 | 4/14/2006 | 4/14/2006 | P | PASS |
Troy James
|
|
|
meet mike wiscom at 1:30 met to discuss where fsd and fd are required at floors 5 through 11 floors
|
Rough-in | 4/13/2006 | 4/13/2006 | 4/13/2006 | P | PASS |
Troy James
|
|
|
ok to cover ceilings at guest bathrooms
|
Rough-in | 3/31/2006 | 4/3/2006 | 4/3/2006 | A | PASS |
Troy James
|
|
|
checked fsd at shafts to floors 9 and 10
|
Rough-in | 3/31/2006 | 3/31/2006 | 4/3/2006 | P | CANC |
Troy James
|
|
|
|
Rough-in | 3/27/2006 | 3/27/2006 | 3/27/2006 | P | FAIL |
Troy James
|
|
|
fsd at shafts to floors 7,8 ok fsd are required where exhaust fan and supply duct have opening into corridor at linen/storage room
|
Rough-in | 3/20/2006 | 3/20/2006 | 3/20/2006 | P | FAIL |
Troy James
|
|
|
ok shafts at floor 5 and 6 see job plans for highlighted shafts, need to verify if corridor penetrations need fsd at 6th floor exhaust to vending area, and supply duct at same location
|
Application received | | | 12/29/2005 | | |
|
|
|
|
Issue permit | | | 12/29/2005 | | DONE |
|
|
|
|