Third Notice MEC | 3/2/2007 | 3/2/2007 | 3/21/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice MEC | 2/5/2007 | 2/5/2007 | 3/2/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 10/18/2006 | 10/18/2006 | 2/5/2007 | | DONE |
Alan Hauser
|
|
|
|
Final | 10/18/2006 | 10/18/2006 | 10/18/2006 | P | PASS |
Alan Hauser
|
|
|
Phone #: ###-#### Internet Inspection Request from: Becky Sucher
|
Final | 10/17/2006 | 10/17/2006 | 10/17/2006 | P | FAIL |
Alan Hauser
|
|
|
raise flue termination up above unit so doesn't blow into outside air opening of next rtu .
|
Final | 10/4/2006 | 10/4/2006 | 10/4/2006 | P | PART |
Alan Hauser
|
|
|
ok for tile, no access to roof because of painting.
|
Rough-in | 8/10/2006 | 8/11/2006 | 8/11/2006 | A | PASS |
Alan Hauser
|
|
|
duct and hard ceiling areas ok for cover, no grid at this time
|
Application received | | | 6/9/2006 | | |
|
|
|
|
Issue permit | | | 6/9/2006 | | DONE |
|
|
|
|