First Notice | 3/31/2009 | 3/31/2009 | 5/4/2010 | | DONE |
Troy James
|
|
|
This permit finaled on the web by PATTY KIRK
|
Final | 3/31/2009 | 3/31/2009 | 3/31/2009 | P | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 3/31/2009 at 7:00:59 AM. Contact: ###-####.
|
Final | 3/3/2009 | 3/4/2009 | 3/4/2009 | A | PART |
Alan Hauser
|
|
|
all gas done and hooked up, except in lab rooms to tables
|
Pressure Test | 2/24/2009 | 2/25/2009 | 2/25/2009 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 2/24/2009 at 2:41:21 PM. Contact: ###-####. gas ok over locker area
|
Rough-in | 1/29/2009 | 2/2/2009 | 2/2/2009 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 1/29/2009 at 4:16:00 PM. Contact: ###-####. all hydronics ok
|
Rough-in | 12/10/2008 | 12/10/2008 | 12/10/2008 | P | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 12/10/2008 at 10:41:29 AM. Contact: ###-####. complete test to 5# system
|
Pressure Test | 11/17/2008 | 11/17/2008 | 11/18/2008 | P | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 11/17/2008 at 9:08:17 AM. Contact: ###-####. see plans for areas test and approved
|
Pressure Test | 10/15/2008 | 10/15/2008 | 10/16/2008 | P | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 10/15/2008 at 9:41:34 AM. Contact: ###-####. 20# test to science rooms building G and H
|
MEC-Aging Inspection | 9/17/2008 | 9/17/2008 | 9/17/2008 | | CANC |
Troy James
|
|
|
|
MEC-Aging Inspection | 7/15/2008 | 7/15/2008 | 7/15/2008 | | CANC |
Troy James
|
|
|
|
MEC-Aging Inspection | 5/12/2008 | 5/12/2008 | 5/12/2008 | | CANC |
Troy James
|
|
|
|
Application received | | | 2/11/2008 | | |
|
|
|
|
Issue permit | | | 2/11/2008 | | DONE |
|
|
|
|