Final | 8/6/2010 | 8/6/2010 | 8/6/2010 | A | PASS |
Troy James
|
|
|
|
Rough-in | 7/6/2010 | 7/6/2010 | 7/6/2010 | A | PASS |
Troy James
|
|
|
ok to cover, still need to inspect inline fan in attic and connecting duct at final
|
Rough-in | 7/1/2010 | 7/1/2010 | 7/1/2010 | P | PART |
Troy James
|
|
|
Please contact Gary at ###-#### for inspection.
Thank you Inspection requested from web by: Stephanie Brown framing contractor will have to install 2' wide platform from attic access to exhaust unit with light and switch. Contractor will install this before approved rough inspection. Also need permit and gas piping in wall tested for cover. Exhaust fan is back ordered ok to cover. Will inspect duct rest of duct and fan in attic later.
|
Application received | | | 6/28/2010 | | DONE |
|
|
|
This permit was created on the web by Stephanie Brown
|
First Notice | 8/6/2010 | 8/6/2010 | | | |
Troy James
|
|
|
|